Delta Building Group, Inc. v. Michael A. Laurenzano and Livia A. Laurenzano and Newcomer Lumber and Supply Co., Inc., et al.
State: Indiana
Court: Court of Appeals
Docket No: 55A04-0611-CV-653
Case Date: 09/28/2007
Preview:FOR PUBLICATION

ATTORNEY FOR APPELLANT: BRIAN C. MAIER Brian C. Maier, P.C. Indianapolis, Indiana

ATTORNEYS FOR APPELLEE: SHIV GHUMAN O'NEILL MARK A. VOIGTMANN Baker & Daniels, LLP Indianapolis, Indiana

IN THE COURT OF APPEALS OF INDIANA
DELTA BUILDING GROUP, INC., Appellant/Interpleader Defendant, vs. MICHAEL A. LAURENZANO AND LIVIA A. LAURENZANO, Appellees/Interpleader Plaintiffs, and NEWCOMER LUMBER AND SUPPLY CO., INC., ILLG CONSTRUCTION, CLINE EXCAVATING, THERMOCORE PANEL SYSTEMS, WINDOW ONE, and SUBURBAN STEEL COMPANY, Appellees/Interpleader Defendants. ______________________________________ NEWCOMER LUMBER & SUPPLY CO., INC. Appellee-Plaintiff, vs. DELTA BUILDING GROUP, INC. ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) )

No. 55A04-0611-CV-653

and MICHAEL A. LAURENZANO and LIVIA A. LAURENZANO, Appellees-Defendants. ______________________________________ WINDOW ONE, Appellee/Cross-Plaintiff, vs. ABN AMRO MORTGAGE GROUP, INC., Appellee/Cross-Defendant. ______________________________________ THERMOCORE PANEL SYSTEMS, Appellee/Cross-Plaintiff, vs. ABN AMRO MORTGAGE GROUP, INC. Appellee/Cross-Defendant.

) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) )

APPEAL FROM THE MORGAN SUPERIOR COURT The Honorable G. Thomas Gray, Judge Cause No. 55D01-0502-CC-81

September 28, 2007

OPINION - FOR PUBLICATION

CRONE, Judge

Case Summary Delta Building Group, Inc. ("Delta") appeals the trial court's finding in favor of Michael A. Laurenzano and Livia A. Laurenzano (collectively "the Laurenzanos") on their complaint for interpleader. We affirm. Issue The dispositive issue is whether the trial court violated the Uniform Arbitration Act ("the UAA") by improperly modifying or vacating a prior arbitration award. Facts and Procedural History The Laurenzanos contracted with Delta for the construction of a home in Morgan County. They entered into a contract which provided in relevant part as follows: "All claims or disputes between [Delta] and the [Laurenzanos] arising out of, or relating to, the Contract Documents or the breach thereof shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining [sic].... The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with the applicable law in any court having jurisdiction thereof." Appellant's App. at 143-44. In November 2003, the Laurenzanos fired Delta and initiated an arbitration proceeding. Soon thereafter, the Laurenzanos's lender approved a distribution to Delta in the amount of $55,997.80. After receiving letters from the Laurenzanos's counsel, the lender refused to release the money to Delta. Suppliers and subcontractors on the Laurenzanos's house included Newcomer Lumber and Supply Co., Inc., ILLG Construction, Cline Excavating, Thermocore Panel Systems,
3

Window One, and Suburban Steel Company. On December 23, 2003, Window One filed a notice of intent to hold mechanic's lien. On December 30, 2003, Newcomer sent notice of personal liability to the Laurenzanos pursuant to Indiana Code Section 32-28-3-9. On February 10, 2005, Newcomer filed a complaint against Delta and the Laurenzanos. At the arbitration hearing, Delta offered an exhibit listing the amounts it owed to various subcontractors--including $28,273.87 to Newcomer Lumber, $6,490.00 to Thermocore, and $15,786.16 to Window One--for work authorized prior to the termination of the construction contract. Appellant's App. at 113. On May 4, 2005, following a two-day arbitration hearing, the arbitrator awarded the Laurenzanos $39,370.00, and he awarded Delta $81,200.10, resulting in a net amount of $41,830.10 owed by the Laurenzanos to Delta. The arbitrator ordered the Laurenzanos to pay this amount to Delta within thirty days. Pursuant to Rule 47 of the Construction Industry Arbitration Rules of the American Arbitration Association, the Laurenzanos and Delta each filed a request for modification of the arbitrator's award. The Laurenzanos's submission included the following request: 5. Newcomer Lumber has filed suit against Delta and the Laurenzanos and Window One has placed a lien on the Laurenzanos' home. In order to prevent further litigation related to the contract between the Laurenzanos and Delta and to allow the Laurenzanos to move forward with the construction of their home, the Laurenzanos respectfully request a clarification of the Award that the net amount paid to Delta is to be applied to the amounts owed to Newcomer Lumber and Window One (by direct payment to those companies). Appellants' App. at 221. In its June 29, 2005, order regarding requests for modification, the arbitrator recalculated the net amount owed by the Laurenzanos to Delta as follows:

4

A. B. C.

The Laurenzanos are entitled to recover the total amount (including credits) of $35,514.00. Delta is entitled to recover $81,318.01. The net amount the Laurenzanos owe Delta is $45,804.01.

Id. at 57. Again, the arbitrator ordered the Laurenzanos to pay Delta the net amount within thirty days of the date of its order. The arbitrator's order also stated, "All other requests for modification are hereby denied as being outside the scope of modifications permitted under Rule R-47[,]" and "All other provisions of the original Award not expressly modified by this Order shall remain in full force and effect." Id. at 56, 57. The Laurenzanos did not pay Delta. Rather, on August 1, 2005, they filed in the trial court a complaint for interpleader against Delta and the suppliers and subcontractors. In the complaint, the Laurenzanos stated their intent to deposit the arbitration award amount with the trial court. They asked the court to order Delta and the suppliers and subcontractors to assert their respective claims against the Laurenzanos and against each other, to enjoin all the defendants from initiating or prosecuting any claims in connection with this construction project, to adjudge the claims of those parties seeking any portion of the award amount, and to discharge the Laurenzanos from any further liability in connection with this project. The Laurenzanos also filed a motion to consolidate their action with the action previously filed by Newcomer against Delta and them. On August 29, 2005, the trial court consolidated the two cases. On August 30, 2005, Delta filed its answer and affirmative defenses to complaint for interpleader. Window One filed an answer to the Laurenzanos complaint, which included a counterclaim against the Laurenzanos to foreclose its mechanics lien. The Laurenzanos filed

5

their motion for summary judgment and for leave to deposit funds and for discharge, which included a motion for summary judgment against Newcomer and partial summary judgment as to Window One's claim for attorney fees on its mechanics lien. On September 30, 2005, pursuant to the Uniform Arbitration Act, Delta filed with the trial court its motion to confirm arbitration award. Delta also filed a motion for summary judgment as to the Laurenzanos's complaint for interpleader. On October 6, 2005, the trial court set the Laurenzanos's motion for summary judgment for hearing on December 21, 2005. The next day, the trial court also set Delta's motion to confirm arbitration award against the Laurenzanos "along with all other pending matters" for hearing on December 21, 2005. Id. at 285. In the Laurenzanos's response to Delta's motion to confirm arbitration award, they stated in relevant part: "[C]ontrary to Delta's assertions, the Laurenzanos are not seeking to vacate or correct the Arbitration Award. The admit they owe $45,804.01 (the "Award Amount") as payment for work done on their home and want this Court to confirm that their interpleading the exact amount of Award Amount will fully absolve them from liability." Id. at 182. On October 13, 2005, Window One filed a motion for summary judgment, an objection to Delta's motion for summary judgment, and an objection to the Laurenzanos's motion for partial summary judgment. On October 28, 2005, Newcomer filed a motion for summary judgment and a motion in opposition to the motions for summary judgment filed by Delta, the Laurenzanos, and Window One. On November 3, 2005, the Laurenzanos filed their response to Delta's motion for summary judgment and Window One's countermotion for summary judgment. On November 8, 2005, Window One filed its response to
6

Newcomer's motion for summary judgment. On November 14, 2005, Delta filed its response to Window One's motion for summary judgment. On November 18, 2005, Window One filed its reply to Delta's response to Window One's motion for summary judgment. On November 30, 2005, Delta filed its response to Newcomer's motion for summary judgment. On December 1, 2005, Delta filed its response to Newcomer's motion for summary judgment. On December 15, 2005, Thermocore filed its cross-claim. On December 21, 2005, the trial court heard argument on all pending matters and then took them under advisement. On December 23, 2005, the Laurenzanos paid the net arbitration award of $45,804.01, plus interest in the amount of $76.39, to the Morgan County Clerk. On March 28, 2006, the trial court issued its order, stating in pertinent part: At issue are numerous summary judgments, all of the defendants requesting that Delta and or [the Laurenzanos] pay them monies, which are due from the construction project, and [the] Laurenzanos request that they be absolved from any further liability. Most of these complaints revolve around an award of arbitration issued by an arbitrator on May 4th, 2005, Jerome O. Pitt, arbitrator, and modified on June 29th, 2005 by the arbitrator. The arbitrator balanced off equities and debts owing each party between Delta and [the Laurenzanos] and ordered that [the Laurenzanos] pay Delta Forty-five thousand, eight hundred and four dollars and one cent ($45,804.01). In looking at [the Laurenzanos's] motion for summary judgment under affidavit of Shiv O'Neill, is an accompanied document entitled Laurenzano Project Draw No. 3. In that document it sets out the amount of money owed each of the defendant subcontractors under draw 3 to be paid by [the Laurenzanos] to Delta. In that exhibit Illg Construction was due Seven Thousand ($7,000.00), Cline Excavating was due Five thousand two hundred eighty four dollars ($5,284.00); Newcomer Lumber was due Twenty-eight thousand, two hundred seventy-three dollars and eighty-seven cents ($28,273.86); Thermocore was due Six thousand, four hundred ninety dollars ($6,490.00); Window One was due Fifteen thousand, seven hundred eighty-six dollars and sixteen cents ($15,786.16), Suburban Steel Company was due One thousand, three hundred
7

sixty five dollars and forty-six cents ($1,365.46), and Delta Building Group was due Seven thousand, five hundred twenty-five dollars and fifty-two cents ($7,525.52). That came to a total of Seventy thousand, two hundred and thirtyeight dollars and twenty-one cents ($70,238.21). From that was subtracted a balance from a previous draw of One thousand, five hundred fourteen dollars and twenty-four cents ($1,514.24) leaving a balance now due of Sixty-eight thousand, seven hundred and twenty-three dollars and ninety-seven cents ($68,723.97). That number is within one hundred dollars ($100.00) of the arbitrator's findings due Delta in it's modified order of June 29th, 2005. Therefore, it is obvious to the Court that under the arbitration clause of the contract that all of the defendants and Newcomer Lumber, as plaintiff, amounts due were rolled into the arbitrator's award. If not for the arbitrator's deduction for what he found [the] Laurenzanos were due from Delta, the total amount would have been available for Delta to pay all the construction subcontractors and suppliers their due. Because of the deduction for Delta's wrongdoings as found by the arbitrator, Delta's due has been deducted to an amount of Forty-five thousand, eight hundred and four dollars and one cent ($45,804.01). That amount [the Laurenzanos have] paid into the Court under the interpleader action. Because of the arbitrator's findings all of the defendant subcontractors must seek their compensation from Delta and not from [the Laurenzanos] as to the amounts found by the arbitrator. Id. at 12-13. On April 25, 2006, the trial court issued an order clarifying that its prior order was not a final order in the case. On May 11, 2006, Window One, Newcomer, and Thermocore jointly filed their agreed stipulation regarding the distribution of the funds held by the Morgan County Clerk. The stipulation provided that Newcomer should receive 57%, Window One should receive 33%, and Thermocore should receive 10% of the $45,880.40, deposited by the Laurenzanos. On August 11, 2006, Newcomer filed a notice of submittal of proposed order. On August 17, 2006, the trial court issued an order adopting Newcomer's order. The order stated that because Newcomer was the only subcontractor or supplier that had served notice

8

of personal liability upon the Laurenzanos pursuant to Indiana Code
Download Delta Building Group, Inc. v. Michael A. Laurenzano and Livia A. Laurenzano and

Indiana Law

Indiana State Laws
Indiana Tax
Indiana Labor Laws
Indiana Agencies
    > Indiana Bureau of Motor Vehicles
    > Indiana Department of Corrections
    > Indiana Department of Workforce Development
    > Indiana Sex Offender Registry

Comments

Tips