Find Laws Find Lawyers Free Legal Forms USA State Laws
Laws-info.com » Cases » Michigan » Court of Appeals » 2000 » ROY FICK V LONGS TRI COUNTY HOMES INC
ROY FICK V LONGS TRI COUNTY HOMES INC
State: Michigan
Court: Court of Appeals
Docket No: 216133
Case Date: 07/21/2000
Preview:STATE OF MICHIGAN
COURT OF APPEALS


ROY FICK and BRENDA FICK, Plaintiffs-Appellees, v LONG'S TRI-COUNTY HOMES, INC., Defendant-Appellant, and COMMODORE HOMES, INC., Defendant, . and MARVIN WILCOX, d/b/a/ MARVIN WILCOX CONSTRUCTION, Defendant-Appellee.

UNPUBLISHED July 21, 2000

No. 216133 Lapeer Circuit Court LC No. 96-022331-CK

Before: O'Connell, P.J., and Kelly and Whitbeck, JJ. PER CURIAM. Following the bench trial in this breach of contract action involving allegedly faulty construction of a basement, the trial court entered a $15,000 judgment in favor of plaintiffs Roy and Brenda Fick.1 Defendant Long's Tri-County Homes, Inc. (LTCH) appeals as of right. We affirm.

1

The trial court held that there was no cause of action against Marvin Wilcox. Before trial, the Ficks and Commodore entered into a consent judgment for $2,000.

-1

I. Basic Facts And Procedural History The Ficks bought a double-wide mobile home from LTCH in April 1994. At that time, they contracted with LTCH to construct a basement for the mobile home. LTCH orally agreed to act as the general contractor for the construction, taking a fifteen percent commission on all subcontracting fees. Originally, the parties contracted for a "thirteen-block" basement, i.e. a cement basement consisting of thirteen rows of cement blocks stacked on each other; each cement block is approximately eight inches tall. In mid-December 1994, the Ficks went to the construction site to discuss the building plans with the subcontractor, Marvin Wilcox, and Jerry Wilcox, who was acting as LTCH site coordinator.2 During the discussion, Marvin Wilcox stated that weather constraints would delay construction. However, Jerry and Marvin Wilcox both suggested that construction would not be delayed if the Ficks chose a cement "foam-style" basement, which would consist of sixteen-inch blocks that are insulated on the outside and filled with cement. The Ficks stated that they were unsure what a cement foam basement was, so Jerry and Marvin Wilcox suggested that the Ficks look at an example. During this discussion concerning possible basement design, neither Marvin nor Jerry Wilcox explained to the Ficks how tall their basement ceiling would be with a cement foam basement. However, Marvin Wilcox took the Ficks to Margaret and Hugh Peters' home, which had such a basement. While in the Peters' residence, the Ficks claimed, Marvin Wilcox told them that their basement walls would be at least as tall, if not taller than the eight foot five inch walls they were examining. Additionally, Brenda Fick said, she asked Marvin Wilcox whether the poured concrete foam basement wall would give her the same height as the initial plan and he told her that it would be that tall. Evidently, the Ficks were concerned that, if their ceiling was too low, when they played pool their sticks would leave marks on the ceiling. Marvin Wilcox, testified, however, that he did not recall anyone mentioning ceiling height while the parties were examining the Peters' home. The Ficks ultimately agreed to the cement foam style basement and Marvin Wilcox discussed the billing procedures for the new basement. They decided that Marvin Wilcox would bill LTCH for the basement. However, the Ficks agreed to pay him directly for the additional cost of the new basement and for the cost of a certain style of doors leading to the basement. Marvin Wilcox and LTCH executed a written agreement for constructing the basement, which noted that Marvin Wilcox was to use "12" block 13 block [sic] high," but did not specify whether those blocks were standard cement or foam. Nor did that agreement indicate any height for the basement ceiling. Marvin Wilcox constructed a thirteen-block basement out of cement foam and Jerry Wilcox went to the site periodically to inspect all the subcontracted work. In January 1995, Marvin Wilcox completed the basement and LTCH paid him nearly $18,000 for the work. Later that month, the Ficks' house was set on the basement and the other subcontractors LTCH hired finished the electrical wiring and plumbing. In February or March 1995, when the Ficks were hanging drywall in their basement, they discovered for the first time that their basement ceiling was not eight feet tall, as
2

Marvin and Jerry Wilcox are brothers.

-2

requested, but only about seven feet tall. Brenda Fick complained to LTCH immediately, but still closed on the home that same month because she did not see withdrawing from the transaction was a possibility at that late date. This low ceiling prevented the Ficks from using the chimney for the wood stove installed in the basement because of local building codes. At trial, plaintiffs' expert in residential building stated that he had measured the Fick's basement and concluded that it is equivalent to an eleven-block basement, not a thirteen-block basement, if measured from the floor to the ceiling, excluding the knee wall. The expert estimated that it would cost the Ficks approximately $20,230 to add an extra sixteen-inch block to the basement in order to raise the ceiling. LTCH's expert in basement installation and mobile home foundations stated that a thirteen block wall ordinarily measures eight feet, four inches from the top of the footing to the top of the structural wall, depending on the type of home. He estimated that the Fick's basement walls were between seven and eight feet high and equivalent to a thirteen-block wall including the knee wall, but that the Ficks would need a fourteen- or fifteen-block wall to have an eight-foot ceiling clearance. The Ficks could increase the headroom in their basement if they inserted a larger knee wall and reset the house, but that would be impractical and involve "considerable expense" because it would require rewiring and replumbing. He did not advocate inserting an additional sixteen-inch block because doing so typically leads to structural problems. LTCH's expert did say that he was in the practice of telling customers that a double-wide home's basement wall is shorter than basement walls in other homes. He conceded that this lower height would not be immediately apparent to an average customer without construction experience who hears about a thirteen-block wall and assumes that there will be a full 104 inch clearance when the eight-inch blocks are stacked on each other. LTCH's office manager, Kimberly Gerstenberger thought that the Ficks could repair their basement for far less than the Fick's expert estimated. For instance, she thought that it would cost less than $2,000 to making heating adjustments and closer to $2,000, not $6,000, to lift the house off the foundation. The trial court rendered it decision from the bench. First addressing the question of contractual privity between the Ficks and Marvin Wilcox, the subcontractor, concerning the basement construction, the trial court found that there was no privity. The Ficks and Wilcox never entered into a written agreement. Rather, Marvin Wilcox entered into an agreement with LTCH to construct the basement and LTCH in turn had a contract with the Ficks to act as their general contractor. Accordingly, the trial court rejected the idea that Marvin Wilcox could be held liable for any construction defects, rather than LTCH, because he specifically acted as LTCH's agent or subcontractor. As for the breach of contract claim against LTCH, the trial court found that the contract between LTCH and the Ficks had three parts. The first part was LTCH's agreement in writing to act as the Ficks' general contractor for a fifteen percent fee. The second part was LTCH's agreement with Marvin Wilcox to construct a thirteen-block basement. The third part was Marvin Wilcox's

-3

representation that the Ficks' ceiling would be higher than the one in the Peters' home, which the trial court considered "an oral representation which clarifies the contract and is part of the contract." Because of these additional representations, the trial court rejected LTCH's suggestion that, if the Ficks' wall met industry standards, it fully complied with the contract. In light of these contractual provisions, the trial court examined the evidence adduced at trial, noting that a thirteen-block wall is a term of art in the construction industry and does not clearly indicate how high the resulting wall and ceiling would be in a basement made that way. The trial court did not find a defect in the construction itself. Nor did it question that there were many other homes with the same ceiling clearance. However, the trial court concluded that, pursuant to the parts of the contract it identified, Plaintiffs would receive a basement with a ceiling height at the most equivalent to the Peters' home and at least they would have a contract for a ceiling height of 100 inches which is the clearance for a 13 block wall for anything other than a mobile home. If it's stick built, I believe you're going to have a 100 foot [sic] of clearance in the ceiling or if it's a modular, you're going to have 100 inches. Sure, there may be some duct work in those constructions that may cut into that but it's nowhere near the intrusion that you have with a mobile home where you've got beams every twelve feet and the rest of the support system and the result of that is . . . Plaintiffs actually got . . . about 84 inches of ceiling clearance and that's a significant difference of about 16 inches and that is significant. That is significant and I'm not saying either that some people don't receive that on a regular basis and live with it but I don't think the Plaintiffs contracted for or expected that. Again, the consequence of that is that if they want a ceiling below the lowest beam and if it's a suspended ceiling or a ceiling with any kind of framing under it, they're going to be down to six and a half or six and three-quarters feet of clearance and I think that's unreasonable or if they want to box in the beams and put a higher ceiling in, they can but then they're going to have false beam boxes every twelve feet to that ceiling. I don't think they bargained for that either. The trial court rejected LTCH's argument that they were forced to install the shorter wall because of engineering concerns and commented that "in a lot of these the defenses that are raised, a lot of it comes down to a question of but if the Plaintiffs had known that, they may have had a choice" to spend additional money to obtain what they desired or reconsider their plans altogether. Although the Ficks may have been able to complain about the basement before instituting this action, the trial court said, they had few choices about a remedy because it would have been unreasonable at that stage to demand that LTCH redo the entire basement in light of their financial obligations. Finally, having found a breach of contract, the trial court determined that the proper measure of damages in this case would be the cost of repair rather than the difference in value between the bargained-for and actual construction. In light of the overall cost of the home project, which was near

-4

$100,000, the trial court determined that repairing the basement for $20,000 to raise the ceiling was expensive but reasonable. The court deducted $5,000 from the award for the Ficks' failure to mitigate their damages and also some additional costs of repair that it found unnecessary, resulting in a $15,000 judgment. II. Arguments On Appeal On appeal, LTCH advances three arguments. First, it contends that if there was a contract for a higher basement ceiling, the contract was between the Ficks and Marvin Wilcox, the subcontractor. Accordingly, the trial court erroneously determined that there was no privity of contract between the Ficks and Marvin Wilcox, and therefore that he was not the liable party. Second, LTCH asserts that the trial court erred when it found that it breached its contract with the Ficks. Finally, LTCH argues that the trial court incorrectly measured the damages in this case. III. The Trial Court's Findings A. Standard Of Review We review the trial court's findings of fact supporting its decision that there was no privity of contract between Marvin Wilcox and the Ficks and that LTCH breached its contract with the Ficks for clear error.3 "A finding of fact is clearly erroneous when, although there is evidence to support it, the reviewing court is left with a definite and firm conviction that a mistake has been made."4 B. Subcontractor As Agent LTCH first challenges the trial court finding that Marvin Wilcox was its agent and, therefore, LTCH could be held liable for Marvin Wilcox's work. We do not find that this finding was clearly erroneous. "An agency relationship may arise when there is a manifestation by the principal that the agent may act on his account."5 An agent with either actual or apparent authority may bind a principal; apparent authority exists when "acts and appearances lead a third person reasonably to believe" that there is an agency relationship.6 In determining whether an agent had apparent authority, this Court looks to all the surrounding facts and circumstances, and d etermines whether an ordinarily prudent person would be justified in assuming that one had the authority to bind another.7

3 4

MCR 2.613(C).

Bracco v Michigan Technological Institute, 231 Mich App 578, 584; 588 NW2d 467 (1998),
quoting In re Forfeiture of $19,250, 209 Mich App 20, 29; 530 NW2d 759 (1995).


5

Meretta v Peach, 195 Mich App 695, 697; 491 NW2d 278 (1992), citing 1 Restatement Agency,
2d
Download ROY FICK V LONGS TRI COUNTY HOMES INC.pdf

Michigan Law

Michigan State Laws
Michigan Court
Michigan Tax
Michigan Labor Laws
Michigan State
    > Michigan Counties
    > Michigan Zip Codes
Michigan Agencies

Comments

Tips