SUPERIOR COURT OF NEW JERSEY
APPELLATE DIVISION
DOCKET NO. A-734-98T2
FIRST INDEMNITY OF AMERICA
INSURANCE COMPANY,
Plaintiff/Respondent,
v.
DAVID KEMENASH,
Defendant/Third-Party
Plaintiff/Appellant
and
KATHLEEN KEMENASH, NICOLE
KEMENASH, DAVINA KEMENASH,
and NDK GENERAL CONTRACTORS,
INC.,
Defendants/Third-Party
Plaintiffs,
v.
PATRICK LYNCH,
Third-Party Defendant.
Argued: November 29, 1999 - Decided: February 10, 2000
Before Judges Keefe, A.A. Rodríguez and
Lintner.
On appeal from Superior Court of New Jersey,
Law Division, Cumberland County.
Todd W. Heck argued the cause for appellant
(Basile & Testa, attorneys; Mr. Heck, on the
brief).
Robert E. Nies argued the cause for
respondent (Wolff & Samson, attorneys; Mr.
Nies, of counsel; Robert L. Tchack, on the
brief).
The opinion of the court was delivered by
Keefe, J.A.D.
Defendant David Kemenash appeals from an order granting
partial summary judgment to plaintiff First Indemnity of America
Insurance Company (FIA) in the amount of $3,248,171.17, plus
prejudgment interest. The judgment was on "fewer than all the
claims as to all parties," but was certified as final. R. 4:42
2. Although defendant did not move for leave to appeal as
required by the Court Rules, we now grant leave to appeal on our
own motion. See Pressler, Current N.J. Court Rules, comment on
R. 2:5-6 and R. 4:42-2 (19). We affirm.
Defendant owned a corporation, D. Kemenash & Associates,
Inc. (DKA), a general contractor. DKA defaulted on two municipal
construction projects for which plaintiff had acted as surety.
Plaintiff completed the projects under separate takeover
contracts with the municipality. Then, relying on an indemnity
agreement signed by defendant and his wife, plaintiff alleged it
was entitled to reimbursement from defendant and his wife
personally. Defendant, however, asserted that he had never
provided plaintiff with an indemnity agreement for his
construction business, and that the agreement on which plaintiff
relied was signed in favor of another surety and placed in the
possession of his insurance broker.
On appeal, defendant argues that the trial judge erred in
denying his summary judgment motion premised on the six year
statute of limitations, and erred in granting plaintiff summary
judgment because he improperly applied the summary judgment
standard, by failing to grant defendant all favorable inferences
and ignoring numerous areas of factual dispute. Finally,
defendant challenges the judge's award to plaintiff of over
$650,000 in prejudgment interest.
DKA was a commercial construction company that did a
considerable portion of its work on large federal government and
public works projects. It was in business from May 31, 1978,
until mid-1991 when the company ceased work, having filed for
bankruptcy.
As a standard requirement for each public works project on
which DKA submitted a successful bid, DKA was required to obtain
a performance bond. Although the precise date is unclear from
the record, from at least the spring of 1984 until the spring of
1989, DKA obtained its bonds exclusively through a bonding
agency, Comsur, Inc. ("Comsur"). Also during the same period,
Travelers Insurance Company of Hartford ("Travelers") acted as
the exclusive bonding company for DKA. As a guarantee for the
bonds issued by Travelers, defendant and his wife signed
indemnity agreements. Sometime in the spring of 1989, Travelers
informed defendant that it no longer would be able to act as
commercial surety for DKA because it had sold its surety bonding
division.
On May 4, 1990, plaintiff executed performance and payment
bond #026696 for DKA in the amount of $5,289,000 on behalf of the
Cape May County Municipal Utilities Authority ("MUA"). The space
designated for the description of the bonded project is blank,
but the parties agree that this project involved construction of
a sanitary landfill ("the landfill project"). On May 9, 1990,
plaintiff executed performance and payment bond #026689 for DKA
in the amount of $1,848,000 on behalf of the MUA with respect to
DKA's construction of a bulky waste sorting/recycling facility
and transfer station ("the bulky waste project"). These were the
only two performance bonds plaintiff issued on DKA's behalf.
On April 2, 1991, defendant and his wife filed a voluntary
petition for bankruptcy, and DKA also filed for bankruptcy. At
or about the same time, DKA ceased work and abandoned the two MUA
projects. Thereupon the MUA declared DKA to be in default,
terminated its right to proceed under the contract and demanded
that plaintiff, as surety, complete DKA's work on both projects.
On June 6, 1991, plaintiff and the MUA entered into takeover
contracts whereby plaintiff became the "replacement contractor"
and agreed to assume responsibility to complete both projects to
the extent of the penal sums of each related bond. The contracts
required the MUA to dedicate the remaining construction funds to
completion of the projects, specifically the sum of $1,974,004.48
on the landfill contract and $575,849.26 on the bulky waste
project, subject to reductions for expenses incurred as a result
of DKA's default and the ensuing delay. Plaintiff agreed to
discharge any mechanics liens against the project.
Plaintiff certified to the trial court in this action that,
as to plaintiff's costs on the landfill project, it paid a total
of $3,684,233.56 to claimants and received proceeds from the MUA
of $1,716,459.51. As to the bulky waste project, it paid
$973,444.25 and received $438,734.66 from the MUA. Thus,
plaintiff's loss for the two projects totaled $2,502,483.64.See footnote 11
In January 1992, defendant was convicted in federal court of
submitting fraudulent bank statements and served thirty-nine
months in prison. On July 19, 1993, an order was entered denying
discharge in the bankruptcy cases. The order was based on the
terms of a settlement between defendant and the bankruptcy
trustee wherein defendant agreed to consent to the denial of his
discharge if he were unsuccessful in appealing his criminal
conviction, which he was.
On December 30, 1997, plaintiff filed its complaint in this
matter asserting that defendant and his wife owed plaintiff over
$3,000,000. The basis for its allegations was an indemnity
agreement defendant and his wife signed on June 11, 1984. The
complaint alleged in paragraph 6 that on "June 11, 1984, in
consideration for, and as a precondition of FIA's executing
surety bonds on behalf of DKA, Kemenash, his wife and DKA
executed an Agreement of Indemnity (the "Indemnity Agreement") in
favor of FIA . . . " A copy of that agreement was attached to
the complaint. It provides:
WHEREAS D. KEMENASH & ASSOCIATES, INC.
requires or may hereafter require
suretyship upon certain bonds or obligations
or suretyship and has applied or may
hereafter apply to ______ (hereafter called
the Company) to execute such instruments as
surety.
NOW THEREFORE, should the company execute or
procure the execution of the suretyship for
which application is now pending, or which
may be hereafter applied for, or other
suretyship in lieu thereof, or in lieu of
suretyship now outstanding, or in connection
therewith, the undersigned, hereinafter
called the Indemnitor does . . . agree . . .
Paragraph two of the document reads:
[T]he indemnitor will perform all the
conditions of each said bond or obligation,
and any and all alterations, modifications,
renewals, continuations, and extensions,
thereof, and will at all times indemnify and
save the Company harmless from and against
every claim, demand, liability, loss, cost,
charge, counsel fee, payable on demand of
Surety, whether actually incurred or not,
(including fees of special counsel whenever
by the Company deemed necessary) expense,
suit, order judgment [sic] and adjudication
whatsoever, and any and all liability
therefor, sustained or incurred by the
Company by reason of having executed or
procured the execution of said bonds or
obligations, and will place the Company in
funds to meet same before it shall be
required to make payment, and in case the
Indemnitor requests the Company join in the
prosecution or defense of any legal
proceeding, the Indemnitor will, on demand of
the Company, place it in funds sufficient to
defray all expenses and all judgments that
may be rendered therein.
It is undisputed that in the copy submitted to the court with
plaintiff's complaint, the spaces designated in the document for
the name of the surety company and the address to which
notification of termination was to be sent both remained blank.
On May 15, 1998, plaintiff filed its partial summary
judgment motion. Plaintiff specifically relied on an admission
defendant made in a deposition in the bankruptcy proceeding in
which defendant is the sole named debtor. During this
deposition, defendant stated that plaintiff issued the bonds for
DKA. When questioned whether he and his wife personally
guaranteed the bonds, defendant replied, "I don't believe so, but
it could be that we both do guarantee it, but I'm not sure." He
was then asked, "Do you guarantee them?" and he replied, "Yes."
Plaintiff also included a scheduled list of unsecured
creditors dated April 16, 1991, and filed in the bankruptcy
proceeding for defendant and his wife. The petition listed both
plaintiff and Travelers, each for an "Unknown" amount. In a
scheduled list of creditors for DKA, dated May 15, 1991,
plaintiff and Travelers were also listed as "contingent" debts
for "Unknown" amounts.
On June 12, 1998, Carlos Andujar, an attorney for
defendants, traveled to plaintiff's offices to inspect a document
purported to be the original agreement. The pages of the
document were bound along the left-hand margin "in a natural
form," unseparated. That document contained plaintiff's name in
the designated space, in a typeface different from that used to
type "D. Kemenash & Associates, Inc." on the previous line. The
document contained the original signatures of defendant and his
wife on page three, along with the corporate seal of DKA, dated
1978. Also on page three, "bleeding" through from page four,
were notary seals.
LeFevre, who in 1984 was employed as a notary public by
Comsur, certified that he had notarized the signatures on the
June 11, 1984, document. He stated:
Although FIA's name had not yet been typed
into the first paragraph of the Agreement of
Indemnity at the time Kemenash and his wife
executed the document, I am certain that this
was FIA's standard form of indemnity
agreement. As I had notarized numerous other
agreements, I know that no other surety
company with which Comsur dealt, including
the Travelers Indemnity Company, used that
form of agreement at that time.
On June 16, 1998, defendants submitted papers responding to
plaintiff's partial summary judgment motion and papers supporting
their cross-motion. In their response to plaintiff's statement
of material facts, defendants stated that the "referenced
Agreement [of June 11, 1984] was executed in favor of another
surety company, not FIA." In his accompanying affidavit,
defendant asserted:
7. In 1984, DKA executed a preliminary
Indemnity Agreement in connection with its
recently-formed business relationship with
Travelers. My wife and I joined in the
Indemnity Agreement at the request of Comsur
Inc., who took possession of the document.
8. This Indemnity Agreement was not
executed in favor of the Plaintiff First
Indemnity of American Insurance Company
("FIA"). DKA had no business dealings with
FIA until the Spring of 1989, after Travelers
announced to DKA that it was no longer able
to act as commercial surety for DKA . . . .
15. FIA never obtained an Indemnity
Agreement for bonds it issued in favor of DKA
from DKA, myself, and/or my wife. This is
because when in 1989 DKA first commenced
business with FIA, Travelers already had
substantial, written indemnity rights against
DKA, myself, and my wife (known to both FIA
and Comsur at the time) upon numerous then
incomplete construction projects. FIA made a
conscious decision at the time to only pursue
indemnity agreements from me in connection
with the separate DKR [D. Kemenash Equipment
Sales & Rentals, Inc.] activities.
He also asserted that the version of the indemnity agreement
produced during an FIA representative's deposition was "phony"
and "nothing less than a fraud."
Plaintiff explicitly "[d]isputed that Travelers was the only
surety company with whom DKA dealt between the Spring of 1984 and
mid-1989." It asserted:
In the Spring of 1984, Kemenash and his
broker met with FIA's then-lead underwriter
to ask FIA to execute a bid bond for an out
of-state project that Travelers would or
could not bond. FIA agreed to execute the
bond, provided that DKA, Kemenash and his
wife execute FIA's standard Agreement of
Indemnity. Kemenash agreed, and DKA,
Kemenash and Kemenash's wife thereafter
executed that Agreement of Indemnity, dated
June 11, 1984 (the "Indemnity Agreement").
DKA did not ultimately bid for the out-of
state project, however, and FIA accordingly
did not execute a bid bond for that project.
Defendant denies that such a meeting ever took place. He admits,
however, that he executed an indemnity agreement exactly like the
one upon which plaintiff relies in connection with a surety bond
issued by plaintiff in 1989 for a different company owned by
defendant, D. Kemenash Equipment Sales and Rentals, Inc.
I.
Defendant argues that the trial judge erred in failing to
dismiss the complaint on the ground that it was barred by the
six-year statute of limitations. N.J.S.A. 2A:14-1. The trial
judge held that plaintiff's action was not barred. He said: "It
is clear from a review of all the cases that the plaintiff's
cause of action accrued in this matter when the payments were
made." The judge observed that plaintiff made its last payment
on the bulky waste project on March 14, 1994, and its last
payment on the landfill project on February 4, 1994. He thus
found that "the amount of the plaintiff's loss was not fixed
until after March of 1994."
In his primary argument on this issue, defendant asserts
that plaintiff's cause of action first accrued on June 6, 1991,
when it entered into the takeover contracts with the MUA. Thus,
according to defendant, plaintiff's December 30, 1997, complaint
was filed almost seven months beyond the expiration of the six
year limitations period.
Defendant reasons that, because the terms of the indemnity
agreement provided for contractual indemnification "against mere
claims, demands, and any liability, and not just loss or damage,"
plaintiff's cause of action accrued the moment liability was
imposed upon it. He contends that at that point, on June 6,
1991, when plaintiff signed the takeover contracts, plaintiff was
entitled to maintain an action to recover for breach of the
indemnity contract.
Plaintiff, on the other hand, contends that the indemnity
agreement contained a "bundle of rights," including the "mutually
independent" rights to seek "exoneration" from the indemnitor in
the form of posted collateral sufficient to cover liability and
to "compel indemnifications for any losses actually sustained" by
it. It asserts that "the statute of limitations on a claim for
indemnification for loss begins to run only upon the occurrence
of the loss, which occurs upon settlement of the case, final
judgment against the indemnitee, or payment by the indemnitee."
Plaintiff argues that, as a practical matter, its cause of action
could not accrue until it made payments in excess of the money
owed by the MUA on the underlying contract because "if the
contract balances [paid by the MUA to plaintiff] had exceeded
FIA's payments, FIA would have suffered no loss." It argues that
no authority "bars an action for contractual indemnification
against losses on statute of limitations grounds because the
indemnitee chose not to pursue, or the statutes of limitations
already expired on, its right to seek exoneration or
indemnification for asserted liability."
Recovery on express or implied contractual claims or
liability not under seal is governed by N.J.S.A. 2A:14-1, which
provides that such action must be commenced within six years
"after the cause of any such action shall have accrued." Where
the agreement indemnifies for loss, the cause of action accrues
at the point that the liability is discharged by payment and the
indemnitee suffers an actual loss. Bernstein v. Palmer Chev. &
Olds., Inc.,
86 N.J. Super. 117, 122 (App. Div. 1965). Where the
agreement provides indemnification for liability, the cause of
action arises with the liability and the plaintiff is entitled to
recover the amount necessary to enable it to discharge the
liability itself. North v. North & Son, Inc.,
93 N.J.L. 438, 442
(E.&A. 1919). In this case the agreement included language
regarding both loss and liability, stating that plaintiff would
be indemnified for "every claim, demand, liability, loss, cost,
charge, counsel fee, payable on demand of Surety, whether
actually incurred or not . . . ." No New Jersey case has
considered the question of whether a party indemnified as to
liability and loss in the same agreement may elect to proceed on
either basis, with the concomitant different dates for the
accrual of the action.
We assume for the purpose of this opinion, as defendant has
asserted, that FIA's "liability" on the bond was fixed on June 6,
1991, when FIA executed project "takeover agreements" with the
MUA for the two public construction contracts. Defendant's
assertion that FIA could have instituted action against the
indemnitors on that day is correct, but begs the question before
us. Undoubtedly, FIA could have instituted suit on June 6, 1991,
had it chosen to do so. The question, however, is whether FIA
had the choice to sue either on the accrual of its cause of
action based upon "liability" or elect to sue on the indemnity
agreement when its cause of action for "loss" accrued. Although
in some cases the accrual dates may actually be the same, see
Winne v. Morrissey,
14 N.J. Misc 771, 773 (S.Ct. 1936), in this
case, that is clearly not so. Here, FIA did not sustain a loss
under its bond until such time as it paid out more money to
subcontractors than it was owed by the MUA. According to the
record before us, at the time the takeover agreements were
signed, MUA owed $2,055,194.27 on both projects, after
withholding $394,384.47 for delay expenses. FIA did not pay more
than it was owed on both projects until December 30, 1991, when
it made a payment of $353,626.16 to Cacon, Inc., a subcontractor
of DKA, with respect to the landfill project. Thus, if FIA had
the choice under the indemnity agreement to sue on its right to
be indemnified against loss rather than liability, its complaint
was timely.
Authority on the issue is sparse. In Balbao Ins. Co. v.
Zaleski,
532 A.2d 973, 977 (Conn. App. Ct.), certif. denied,
535 A.2d 1315 (Conn. 1987), the defendant was a contractor who had
individually executed a general indemnity agreement in favor of
the plaintiff. Id. at 974. The plaintiff, as surety, had issued
a performance bond and a labor and material bond to the town of
Chester with respect to the defendant's construction of a school
roof. Ibid. On September 21, 1979, in a letter to the defendant
and the surety, the town alleged that the defendant had abandoned
the project and declared that it was terminating the contract.
Ibid. One of the defendant's suppliers thereafter brought suit
against the surety for payment under the bond and was awarded
judgment on October 27, 1981. Ibid. The surety then commenced
suit against the defendant on the indemnity agreement, serving
the complaint on October 2, 1985. Id. at 974-75. The defendant
argued that the limitations period had begun to run on September
21, 1979, when the plaintiff received notice of the defendant's
default. Id. at 975. The plaintiff asserted that it had begun
on October 27, 1981, when it incurred its first loss. As in this
case, a six-year limitations period applied to the action. Id.
at 974.
The terms of the parties' agreement indemnified the
plaintiff against liability as well as loss. Id. at 977. The
court found that the plaintiff's cause of action "arose at once
upon its becoming liable on the contractor's bond." Ibid.
(quoting Dickson v. United States Fidelity & Guar. Co.,
117 So. 245, 247-48) (Miss. 1928)). The court held:
The immediate right to bring suit against the
defendant accrued to the plaintiff upon the
defendant's default of its roof replacement
contract with the town of Chester. Under the
provisions of [the] general indemnity
agreement, and under the rule of law
concerning a contract which indemnifies
against liability as well as loss, the
plaintiff's cause of action accrued upon the
defendant's default in the underlying
performance and labor and material payment
bonds. This is so notwithstanding the fact
that the plaintiff had not yet suffered a
determined or fixed loss.
[Ibid.]
Thus, the plaintiff's cause of action was barred by the six-year
statute of limitations. Ibid.
We decline to follow the Balbao court's holding for several
reasons. First, the reasoning is flawed. The Mississippi case
relied upon was not a statute of limitations case. Rather, it
was a case in which the question presented was whether the
indemnitee's suit against the indemnitor was premature where the
indemnification agreement permitted a suit based upon both
liability and loss. The Mississippi court held that the contract
between the parties permitted the indemnitee to bring suit when
liability occurred irrespective of loss. Dickson, supra. Simply
stated, the surety was entitled to the benefit of its bargain.
Secondly, and perhaps more significantly, the Connecticut
Legislature overruled Balbao by statute. Republic Ins Co v.
Dinardo Auto Sales,
678 A.2d 516, 519 (Conn. Super. Ct. 1995),
aff'd, 677 A.2d 21 (Conn. App. Ct.), certif. denied, 682 A. 2d
1005 (Ct. 1996). As the latter case noted, Balbao did not
reflect "settled" law in the state at the time it was decided.
Id. at 521.
The more reasoned approach in our view is expressed by the
holding in United States Credit Bureau, Inc. v. Claus,
179 P.2d 36, 37 (Cal. Ct. App. 1947). There, the California appellate
court found two separate "covenants" based on language in an
indemnity agreement that provided the surety with "the right of
immediate action . . . for any 'loss or liability when . . .
paid, adjusted, incurred or assumed . . . whether the same shall
have been actually paid or not.'" Ibid. It held that those
covenants may be treated as separate agreements. Ibid. The
plaintiff thus was permitted to maintain an action for recovery
of actual loss even though the time had expired for an action to
recover on the covenant to indemnify for liability. Id. at 37
38. In Oaks v. Scheiffery,
16 P. 252 (Cal. 1887) and in Globe v.
Larkin,
145 P.2d 633 (Cal. Ct. App. 1944), the only other
instances in which California courts were presented with the
issue at bar, the covenants were held to be distinct from each
other. The California courts' repeated affirmation of this
principle indicates it is well settled there.
The California approach resolves the statute of limitations
issue based on sound, fair principles of law. Most importantly,
it fulfills the expectations of the parties under the clear terms
of their agreement and affords the surety the benefit of its
bargain. Defendant admits that the indemnity agreement in
question provided FIA protection against both liability and loss.
Therefore, defendant cannot claim that he was surprised by FIA's
desire to pursue a claim for actual losses sustained by assuming
DKA's obligation to the MUA. Quite simply, unlike a suit for
indemnification against liability, "[t]his action is for the
recovery of actual damages, and could not be maintained if
nothing had been paid." Oaks, supra, at 253 (emphasis added).
Indeed, a suit against an indemnitor after an indemnitee
experiences actual loss is arguably fairer to the indemnitor
because the computation of damages in such cases is more precise.
On the other hand, when suit is brought by the indemnitee simply
because liability has been established the damage claim against
the indemnitor may be far less precise because the obligation of
the indemnitee to the indemnitor's principal may not yet be
fixed. See e.g., Johnson v. Johnson,
92 N.J. Super. 457, 462
(App. Div. 1966); Standard Surety & Casualty Co. of New York v.
Carvel Industries Corp.,
128 N.J.Eq. 104, 106-07 (Ch. 1940);
North v. North & Son, supra, 93 N.J.L. at 442-43.
The contractual right to proceed against the indemnitor upon
liability being established is for the benefit of the surety. A
surety negotiates for that right in recognition of the
uncertainty as to whether the contractor and/or indemnitor will
have sufficient funds "at some distant day" when the surety's
loss has been fixed to satisfy the obligation to the surety.
Standard Surety & Casualty, supra, 128 N.J. Eq. at 108. Thus,
the right of the surety to proceed when liability is fixed is
usually linked with the obligation of the indemnitor to deposit
collateral sufficient to satisfy all expenses, judgments, and
losses that the surety may incur in the future as a result of its
undertaking under the bond. Ibid. This concept is sometimes
referred to as the surety's right of exoneration. Stulz-Sickles
Co v. Fredburn Const. Corporation,
114 N.J.Eq. 475, 477 (Ch.
1933). Therefore, the surety generally is not interested in
obtaining a judgment against the indemnitor for a sum certain
when it institutes suit upon incurring a liability. Rather, its
interest is to secure the benefit of the indemnitor's promise to
post collateral sufficient to cover the surety's anticipated
future losses.
There may be times, however, where it may be impractical for
the surety to institute suit in reliance on the indemnification
against liability. In cases where as here the indemnitors file
for bankruptcy protection, the surety's right of exoneration may
not be a realistic benefit because the indemnitors' bankruptcy
could place the collateral beyond the surety's reach. It would
be unfair to the surety in such circumstances to have the statute
of limitations begin to run at that time because the sole aim of
the indemnity agreement and the expectations of the parties is to
make the surety whole on its bond undertaking.
(At the request of the Court, Parts II, III and IV of this
opinion have been excluded from publication.)
Footnote: 1 1 ($973,444.25 (claims-bulky waste) minus $438,734.66 (proceeds-bulky waste)) plus ($3,684,233.56 (claims-landfill) minus $1,716,459.51 (proceeds-landfill)). In plaintiff's statement of material facts, it alleged that the total losses, aside from prejudgment interest, amount to $2,589,167.01 (Ja60). In its calculation of interest, it noted that only $1,638,026.57 and $430,484.23 were applied to the "principal" and the remaining sums were applied against "interest which had accrued as of the date the recovery was received."