SYLLABUS
(This syllabus is not part of the opinion of the Court. It has
been prepared by the Office of the Clerk for the convenience of the
reader. It has been neither reviewed nor approved by the Supreme Court. Please
note that, in the interests of brevity, portions of any opinion may not
have been summarized).
In this appeal, the Court reviews a trial courts dismissal of a complaint
based on the entire controversy doctrine.
K-Land Corporation No. 28 (K-Land) was formed for the purpose of acquiring approximately
eighty acres of land in Vineland, New Jersey, that had been approved for
development of a three hundred seventy-nine unit mobile home park (project). Although K-Land
did not hold title to the project site until July 1989, it controlled
the property under an option to purchase. The projects completion was conditioned on
K-Lands construction of an off-site sewer line (force main) and a pumping station
to connect the project to existing facilities of the Landis Sewerage Authority (LSA).
The force main required for the connection was to be a six-inch pipe,
extending approximately 15,000 linear feet.
Prior to beginning the construction of the force main, K-Land entered into discussions
with LSA regarding sewer services to the Project. At that time, LSA, which
realized that there would be a need to service existing and future property
owners, requested K-Land to increase the size of the force main from six
to eight inches and to increase the size of the pumping station in
order to accommodate additional service to those potential users. K-Land agreed to do
so, but asked that LSA apply a fair share policy allowing for contribution
by other users according to their fair share of the cost of the
force main and the pumping station. K-Land also asked LSA to provide a
credit against connection fees for costs incurred by K-Land in constructing the force
main to the extent that those costs were not offset by the contributions
from other users. While discussions continued with LSA concerning those issues, K-Land installed
the eight-inch force main at a cost of approximately $400,000.
In October 1999, after the force main already had been installed, the City
of Vineland (Vineland) inquired of K-Land whether the force main would be dedicated
to LSA. K-Land responded, indicating that the force main eventually would be owned
by LSA, noting however that the cost of installation or the allocation of
such costs was a completely different issue from that of ownership of the
force main and appurtenances once installed.
While discussions still were ongoing with LSA regarding the application of a fair
share policy and of credits toward the cost of the force main, K-Land
was engaged in discussions with Berrymans, a mobile park owner and potential user
of the proposed sewer facility. In a September 1990 letter to K-Land, LSA
agreed with K-Land to a basic fair share policy, allowing for the certification
of costs for the force main and pumping station and requiring that future
users pay their fair share of the costs to LSA, which in turn
would disburse the payments to K-Land. However, LSA did not agree to provide
K-Land with credits against connection fees for the unreimbursed costs. Moreover, according to
LSAs connection fees schedule set forth in its letter to K-Land, Berrymans would
be required to pay its connection fees prior to connecting to LSAs sewer
system.
That notwithstanding, Berrymans was willing to proceed in order to obtain its sewer
service, and proposed to K-Land that Berrymans and another potential user assume responsibility
for obtaining a permit and constructing the regional pumping station. Berrymans further proposed
a plan for cost apportionment, should K-Lands costs in constructing the force main
exceed its pro rata share of constructing the pumping station. Although that proposal
was reduced to an agreement signed by Berrymans, the agreement never was implemented
because of LSAs connection fee policy. While the matter remained unresolved, the owners
of K-Land filed for bankruptcy on February 1, 1991. As a result of
K-Lands financial difficulties, neither construction of the pumping station nor development of K-Lands
project proceeded as scheduled.
In July 1991, Vineland filed a complaint against K-Land, Berrymans, LSA, and the
County of Cumberland, seeking only a declaratory judgment concerning the ownership of the
eight-inch force main, which had been constructed by K-Land partially on rights-of-way owned
by Vineland. Vineland specifically sought a judgment establishing ownership of the existing sewer
line either with Vineland or with LSA. Counsel for K-Land attended a conference
regarding the declaratory judgment litigation in order to evaluate the suit and its
need to participate in it. K-Land never filed an answer to the complaint,
apparently based on its conclusion that the pending declaratory litigation did not involve
the issues of fair share assessments and credits against connection fees, issues independent
of the ownership issue, which formed the basis of the declaratory action. Eventually,
default judgment was entered against K-Land.
Thereafter, the remaining parties discussed a settlement in the declaration litigation, culminating in
a consent judgment filed in June 1992. Under the consent judgment, to which
K-Land was not a party and in which K-Land did not participate, Berrymans
would be responsible only for its proportionate share of the cost of the
construction of the pumping station, and did not provide for payment of the
fair share costs of the force main from Berrymans or any other potential
user. By its terms, the consent judgment was inconsistent with the tentative status
of discussions between K-Land and LSA, as reflected in LSAs September 1990 letter
to K-Land.
Once K-Lands attorney became aware that the terms of the consent judgment were
prejudicial to its right of reimbursement and that it went beyond the issue
of ownership, he sought to negotiate directly with counsel for LSA and Berrymans,
hoping to avoid further litigation. After those negotiations proved fruitless, K-Land filed suit
against LSA and Berrymans seeking relief, including invalidation of the earlier consent judgment.
Before the trial court, K-Land maintained that its rights against LSA did not
accrue until LSA permitted other users to use the force main without contributing
their fair share. Accordingly, it did not file a cross-claim against LSA in
the declaratory judgment action because that litigation addressed only issues of ownership. K-Land
asserted that its claim against LSA did not accrue until LSA entered into
a consent judgment excusing Berrymans from contributing to the cost of the force
main.
The trial court granted LSAs and Berrymans motions to dismiss, based on the
entire controversy doctrine. The court concluded that K-Lands suit was precluded because it
should have been involved in the first litigation, wherein the ownership of the
line would be resolved and where any credits or any permission to use
that line would have been involved. In an unreported opinion, the Appellate Division
affirmed, finding that the 1991 litigation presented a full and complete opportunity for
K-Land to litigate the issues presented in the litigation K-Land now sought to
pursue. The panel noted that although the original declaratory complaint sought only a
declaration as to ownership of the sewer line, it was not entirely unpredictable
that other related issues, such as the reimbursement issues K-Land now sought to
pursue, would arise and might be discussed and resolved in the course of
that litigation.
The Supreme Court granted K-Lands petition for certification.
HELD : K-Lands suit seeking compensation for and declaration of matters not encompassed by
an earlier declaratory action, in which it intentionally did not participate, is not
barred by the entire controversy doctrine.
1. The Court authorized rule amendments to eliminate mandatory party joinder under the
entire controversy doctrine and to abrogate preclusion of a successive action against a
person not joined in the initial action except in cases involving inexcusable conduct
and clear prejudice. (pp. 16-18)
2. The leading cases establishing and applying the entire controversy doctrine as a
bar to the subsequent assertion of omitted claims have involved deliberate and calculated
claim-splitting strategies designed to frustrate the orderly administration of justice, as opposed to
an innocent omission by an uninformed litigant. (pp. 18-24)
3. The polestar for the application of the entire controversy rule is judicial
fairness. In this case, the Appellate Division did not focus sufficiently on considerations
of fairness when it observed that the 1991 action was the perfect opportunity
for K-Land to resolve the issues that has been festering for several years.
(p. 24)
4. The Courts interest in mandatory claim joinder should not be viewed as
encouraging or requiring the filing of premature or unaccrued claims. In this case,
to require K-Land to file a cross-claim in the declaratory judgment action to
resolve open issues of reimbursement of and contribution to the cost of the
force main, when the record is silent on whether negotiations were likely to
result in resolution of that issue, transforms the entire controversy doctrine from one
designed to conserve judicial resources to a doctrine designed to encourage litigation. (pp.
24-25)
5. There are other equitable factors in this case that counsel against dismissal
of the K-Land suit, including the fact that the consent judgment affecting K-Lands
reimbursement rights was not entered until after K-Land already had defaulted. In addition,
no prejudice alleged by either LSA or Berrymans justifies preclusion of K-Lands suit.
(pp. 25-26)
Judgment of the Appellate Division is REVERSED and the matter is REMANDED to
the Law Division for further proceedings consistent with the Courts opinion.
CHIEF JUSTICE PORITZ and JUSTICES COLEMAN, LONG, VERNIERO, LaVECCHIA, and ZAZZALI join in
JUSTICE STEINs opinion.
Plaintiff-Appellant,
v.
LANDIS SEWERAGE AUTHORITY,
Defendant-Respondent,
and
BERRYMANS BRANCH, LTD.,
Defendant.
Argued April 29, 2002 Decided July 16, 2002
On certification to the Superior Court, Appellate Division.
Ronald S. Blumstein argued the cause for appellant.
David C. Patterson argued the cause for respondent (Maressa, Goldstein, Birsner, Patterson, Drinkwater
& Oddo, attorneys).
The opinion of the Court was delivered by
STEIN, J.
This appeal involves the entire controversy doctrine. K-Land Corporation No. 28 (K-Land) instituted
this litigation to obtain reimbursement from the Landis Sewerage Authority (LSA or Authority)
of approximately $400,000 that it expended to construct the 15,000-foot force main portion
of a sewer system to be operated by LSA for the benefit of
K-Land and other property owners in the immediate vicinity of K-Lands property. K-Lands
claim against LSA was dismissed by the lower courts because of K-Lands failure
to assert that claim in an earlier declaratory judgment suit instituted by the
City of Vineland (Vineland) to determine that it had title to the force
main, a contention to which K-Land was willing to accede. When the Vineland
suit was instituted, K-Land and LSA tentatively had agreed that LSA would assess
and collect from adjacent property owners their proportionate share of the cost of
the force main and remit the proceeds to K-Land, but had not agreed
on how K-Land would be reimbursed for any remaining deficiency. Because the owners
of K-Land had filed for bankruptcy and because K-Land was largely indifferent to
Vinelands attempt to resolve title to the force main, K-Land defaulted in the
declaratory judgment proceeding. Subsequently, the remaining parties, including LSA and Berrymans Branch, Ltd.
(Berrymans), owner of an adjacent mobile home park and one of the largest
property owners to be served by the sewer system, entered into a consent
judgment. One term of that judgment was that Berrymans would pay to LSA
its proportionate share of LSAs cost to construct the sewer systems pumping station,
the clear implication being that Berrymans would not be required to contribute to
the force main.
Although the Appellate Divisions unreported opinion recognized that a cross-claim by K-Land against
LSA in the declaratory judgment suit would have been premature until the consent
judgment was entered (at which time K-Land already had defaulted), the court sustained
the Law Divisions dismissal of K-Lands claims against LSA under the entire controversy
doctrine. We granted certification,
171 N.J. 338 (2002), and now reverse.
The City sought a declaratory judgment [e]stablishing ownership of the existing sewer line
with the City of Vineland, or in the alternative with LSA.
While bankruptcy proceedings were still ongoing, the Kaplans retained attorney Scott F. Jamison
(Jamison), who previously had been an in-house attorney for the Kaplans but now
had a private practice. Jamison still was handling non-bankruptcy litigation for the Kaplans.
In order to evaluate the suit, Jamison requested and received an extension of
time within which to file an answer to Vinelands complaint. Jamison appeared on
behalf of the Kaplans at a scheduled conference regarding the declaratory judgment litigation.
There now is some dispute concerning what was said at that conference.
According to the certification of Joseph P. Testa, who was then counsel for
LSA,
counsel for K-Land indicated that he was aware that he had not filed
any responsive pleadings as of that date, and indicated to the Court and
all other counsel that he would be doing so immediately which would include
various counts against [the City, LSA] and Berrymans Branch, Ltd. He further represented
that he would present issues dealing with his clients Agreement and arrangement with
Berrymans Branch, Ltd on construction of the sewer line and pump station to
service his clients proposed mobile home project. He further represent[ed] that he would
present issue[s] concerning [LSA] in regard to the assessment and manner of calculating
the connection fee to be charged to his client by the Authority, the
manner of allocating sewer capacity to his client, reimbursements and credit due to
his client for construction of the sewer line to service his clients proposed
mobile home park and the ownership of the sewer line.
The certification of James J. Gruccio, counsel for Berrymans, states:
During the conference . . . Mr. Jamison indicated that, while he had
not yet done so, he fully expected to file a responsive pleading on
behalf of K-Land . . . [and] that K-Land had various affirmative claims
against Berrymans as well as [LSA]. . . . Mr. Jamison explained that
the claims against Berrymans involved an alleged agreement entered into between Berrymans and
K-Land regarding the construction of the force main. Mr. Jamison indicated that the
claims against [LSA] involved the connection fees charged and the alleged reimbursement agreements
related to the force main. Mr. Jamison indicated . . . that these
allegations would form the basis of the cross claims to be asserted by
K-Land when it filed its answer.
The certification of Ronald S. Blumstein, who was then the only remaining in-house
attorney for the Kaplans after they filed for bankruptcy, asserts:
Mr. Jamison was asked to look into the litigation initiated by the City
of Vineland to determine whether we needed to expend any of our limited
and already overly stretched resources in this litigation, in order to preserve K-Lands
rights . . . . My recollection is that Mr. Jamison reported back
to me that he had attended an initial conference in the case. He
reported that he had advised the other parties to the action that K-Lands
position had always been that the force main would ultimately be dedicated to
either the City or the Authority upon completion and acceptance. . . .
Mr. Jamison indicated that there was some discussion regarding K-Lands position with respect
to the fair share concept and credits against connection fees, but everyone also
acknowledged that those issues were separate and apart from the ownership issue. Following
this discussion, Mr. Jamison and I concluded that K-Land did not have to
continue in this litigation, inasmuch as K-land did not have an interest in
the Courts determination as to whether the force main would ultimately be owned
by the City, the Authority or the County.
Jamisons own certification provides:
I was advised by counsel for the respective parties . . . that
the dispute presented in the action was solely related to the ownership of
the sewer line. . . . It is my recollection that the attorneys
for the City and the Sewerage Authority indicated that they did not have
an objection to K-Land Corp. [] being compensated in accordance with the applicable
statutes and that the issue of reimbursement was a separate issue, not in
dispute. The only dispute involved ownership among the various municipal entities. . .
.
Following this conference, I discussed this matter with my client. It was concluded
that K-Land [] had no objection to either the City or the Sewerage
Authority becoming the owner of the subject line. As a result, no responsive
pleadings were filed in that action by K-Land []. K-Land [] did not
dispute the right of ownership in either the City [or] the Sewerage Authority
and had no objection to the relief sought, as it was solely limited
to ownership.
There was a subsequent meeting among counsel that Jamison did not attend. Following
that meeting, the attorney for Vineland informed Jamison by letter that a default
judgment would be entered against K-Land if a responsive pleading was not filed.
When an answer still was not forthcoming, Vineland entered a default judgment in
January 1992. Subsequently, the remaining parties discussed a settlement in the declaratory judgment
litigation that resulted in a consent judgment filed on June 4, 1992. The
consent judgment, which was signed by counsel for LSA, Berrymans, Vineland and the
County, provides:
The sewer line. . . shall be transferred to the Landis Sewerage Authority
for maintenance and control.
. . . .
[T]he [Authority] will construct a pumping station that will be feasible for the
entire area . . . .
Berrymans Branch will be responsible for their proportionate share of the costs of
the facilities plan and the construction of the pumping station based upon the
amount of gallonage used by Berrymans Branch through said pumping station.
Berrymans Branch agrees to pay their proportionate share of the costs of the
facilities plan and construction of the pumping station based upon their proportionate share
of gallonage payable twenty-five (25%) percent in advance and the remaining seventy-five (75%)
percent of their proportionate share of costs over a four (4) year period
with interest to run at one point above prime, said payments to be
made annually in four equal installments. (For example, if the pumping stations costs
$400,000.00 and it is determined that the amount of gallonage to be used
by Berrymans Branch would be ¼ of the total gallonage used by the pumping
station, then Berrymans Branch would owe $100,000 with 25% down and 75% payable
over four years with interest).
[LAS] and Berrymans Branch further agree that in no event shall Berrymans Branchs
proportionate share be any greater than One Hundred Thousand ($100,000.00) Dollars in the
event the total cost of the pumping station should exceed the estimated Four
Hundred Thousand ($400,000.00) Dollar figure.
Berrymans will hook up all of the existing units, . . . plus
all the new expansion units to [LAS] paying connection fees for the new
units constructed as they are hooked up, but as to the existing []
units they will pay those connection fees financed over the next four years
with interest at one point above prime, said payments to be made annually
in four equal installments. . . .
By its terms, the consent judgment appears inconsistent with the tentative status of
the discussions between LSA and K-Land as reflected in LSAs September 1990 letter
to K-Land. Pursuant to paragraph 11 of LSAs letter to K-Land, LSA would
have the right to collect assessments from potential users of the sewer system
and place in escrow for K-Land, a pro rata share of the [force
main] construction costs. However, under the consent judgment between LSA, Berrymans, Vineland and
the County, Berrymans would be responsible only for its proportionate share of the
cost of the construction of the pumping station. The consent agreement did not
provide for payment of the fair share costs of the force main from
Berrymans or any other potential user.
As indicated, K-Land took no part in negotiations leading to the consent judgment,
having earlier been defaulted. However, after K-Lands attorney became aware that the terms
of the consent judgment were prejudicial to K-Lands right of reimbursement and that
it went beyond the issue of ownership, he sought to negotiate directly with
counsel for LSA and Berrymans, hoping to avoid further litigation. After those negotiations
proved fruitless, K-Land instituted an action against LSA and Berrymans in September 1994,
about twenty months after the default judgment against it in Vinelands suit. The
first count of the complaint sought judgment against LSA compelling it to either
reimburse K-Land . . . for the cost of constructing the force main
or compelling it to impose and collect a special assessment from all future
users of the regional sewer system and reimburse K-Land [] therefrom. Another count
sought a judgment declaring that [LK-Land] is entitled to a credit against or
waiver of connection fees from LSA equal to its cost of installing the
force main. Yet another count sought compensatory damages against Berrymans as a result
of Berrymans breach of the alleged agreement with K-Land to construct the pumping
station. A final count sought judgment declaring that the execution of the consent
judgment in the earlier declaratory judgment action was invalid.
Before the trial court, K-Land contended that it had certain rights associated with
its construction of the force main and merely sought to be treated in
a manner substantially equal to the manner in which LSA treated all other
users of its sewer system. K-Land maintained that those rights did not accrue
until such time as LSA permitted other users to use the force main
without contributing their fair share. Accordingly, K-Land did not file a cross-claim against
LSA in the declaratory judgment litigation because that litigation addressed only issues of
ownership. K-Land asserted that any claim against LSA because LSA excused Berrymans from
contributing to the cost of the force main did not accrue until the
consent judgment was entered.
The trial court granted LSAs and Berrymans motions to dismiss based on the
entire controversy doctrine. See R. 4:30A. The court concluded that the lawsuit was
precluded because K-Land should have been involved in the first litigation, wherein the
ownership of the line would be resolved and where any credits or any
permission to use that line would have been involved. It added that [o]bviously,
the ownership of that line implies the right to the use of that
line. But if the ownership of the line was determined to belong to
the sewerage authority, certainly the use of that line would be pursuant to
whatever rules and regulations the [A]uthority had formulated. It declined to consider principles
of equity, determining that the law would [not] allow [it] to get into
the equities and the unfairness of the remedy in a case under these
particular facts.
The Appellate Division affirmed in an unreported opinion, finding that [t]he 1991 litigation
presented a full and complete opportunity for K-Land to litigate the issues now
presented in the 1994 action. The court determined that K-Lands counsel understood fully
that the reimbursement issues could be raised by way of cross-claim in the
declaratory judgment action, notwithstanding his assertion that he viewed them as a separate
issue from the [issue of] ownership. Even though it acknowledged that the issues
raised by K-Land would have been somewhat premature, the court determined that those
issues still should have been raised and, if necessary, reserved for disposition at
a later time. The court seemed to view K-Lands assertion that its claims
had not accrued because of its ongoing discussions with LSA as contradicted by
the fact that the present suit raises issues regarding reimbursement and contribution that
were unresolved when the force main first was constructed. It concluded that [a]lthough
the complaint only sought a declaration as to ownership of the sewer line,
it was not entirely unpredictable that other related issues would arise and might
be discussed and resolved in the course of the litigation, as did occur
through the consent judgment.
. . . .
The rule as to claim joinder continues to require, as a general matter,
that all aspects of the controversy between those who are parties to the
litigation be included in a single action.
. . . .
[T]he equitable nature of the doctrine[] bar[s] its application where to do so
would be unfair in the totality of the circumstances and would not promote
any of its objectives, namely, the promotion of conclusive determinations, party fairness, and
judicial economy and efficiency.
. . . .
Nor does the doctrine apply to bar component claims either unknown, unarisen or
unaccrued at the time of the original action.
[Pressler, Current N.J. Rules, comments 1 & 2 on R. 4:30A (2002) (emphasis
added).]
In determining the appropriate scope of the entire controversys claim joinder requirement, it
is significant that
the leading cases establishing and applying the entire controversy doctrine as a bar
to the subsequent assertion of omitted claims appear to have involved deliberate and
calculated claim-splitting strategies designed to frustrate the orderly administration of justice, as opposed
to an innocent omission by an uninformed litigant.
[Prevratil v. Mohr,
145 N.J. 180, 203 (1996)(Stein, J., dissenting).]
See, e.g., Massari v. Einsiedler,
6 N.J. 303, 312-13 (1951) (holding that defendant
in initial action brought to recover unpaid purchase price for sale of business
was barred from filing second action for reformation of contract on which initial
action was based); Ajamian v. Schlanger,
14 N.J. 483, 488-89, cert. denied,
348 U.S. 835,
75 S.Ct. 58,
99 L. Ed. 659 (1954)(barring second suit to
recover damages for fraudulent representations brought by assignee of plaintiff that instituted initial
suit for contract rescission based on same alleged misrepresentations); William Blanchard Co. v.
Beach Concrete Co., Inc.,
150 N.J. Super. 277, 293-94, certif. denied,
75 N.J. 528 (1977)(applying rationale of entire controversy doctrine in affirming trial courts ruling barring
filing of amended complaint seeking to assert claims that deliberately were withheld from
pending action); Falcone v. Middlesex County Medical Socy,
47 N.J. 92, 94-95 (1966)(barring
second action by doctor against Medical Society for damages following initial action resulting
in judgment compelling doctors admission in Medical Society).
A recent Appellate Division decision illuminates the equitable limitations on the mandatory claim
joinder requirement. In Hillsborough Township Bd. of Educ. v. Faridy Thorne Frayta, P.C.,
321 N.J. Super. 275 (App. Div. 1999), the issue was whether the Townships
initial suit against contractors and professionals involved in the construction of a new
elementary school to recover damages because of lead-containing solder in the drinking water
barred later suits against those and other parties to recover damages for other
defects known to the Township when the first suit was filed. In 1990,
when the school was completed, the Township learned of the lead-containing solder in
the drinking water as well as two other defects: improper installation of ceiling
fans and water infiltration through the roof and windows. In November 1992, while
the Township negotiated directly with the contractors and their sureties about the ceiling
fans and water leaks, it sued the plumbing contractor (DiNatale) and its surety,
as well as the architect, Faridy Thorne Frayta (Faridy), and the construction manager,
Wagner-Hohns-Inglis (Wagner), for failure to supervise the plumber. The Township was represented successively
by two lawyers, Griggs and Broscious, in that litigation, which eventually was dismissed
against the surety on statute of limitations grounds and all other parties by
stipulation in May 1994. No damages were recovered by the Township.
Negotiations concerning the ceiling fans having been unsuccessful, the Township in August 1995
sued DiNatale, Faridy, Wagner and Middle State, the consulting engineer, alleging negligence in
design, installation and specification of ceiling fans. The trial court dismissed the claims
against Faridy and Wahner on entire controversy grounds. In January 1996, after an
independent expert reported that the water leakage through the roof and windows may
have resulted from design defects, the Township amended its complaint to seek damages
for roof design defects against Faridy, Wagner and Middle State, as well as
Biehn, the general contractor, and Donnelly, the roofing contractor. The amended complaint also
alleged malpractice against Griggs and Broscious, the former lawyers, for failing to join
all claims in the initial suit. Initially, the trial court dismissed the claims
against all defendants, except the lawyers, under the entire controversy doctrine, but on
reconsideration the claims against all defendant other than Faridy and Wagner were reinstated.
The Appellate Division granted leave to appeal sought by Broscious, one of the
malpractice defendants, who asserted that the Township had been unaware when it filed
the first action that the ceiling fan and water leakage problems were attributable
to design defects. The Appellate Division acknowledged that [t]he entire controversy doctrine does
not apply to bar component claims that are either unknown, unarisen or unaccrued
at the time of the original action. Id. at 283 (citation omitted). The
court also referred to this Courts acknowledgment of the doctrines equitable origins:
Although the explicit wording of the rule governing the mandatory joinder of claims
has remained unchanged, the Court continues to emphasize that equitable considerations should ease
the path upon which the doctrinal bar travels. See, e.g., Joel v. Morrocco,
147 N.J. 546, 555,
688 A.2d 1036 (1997) (recognizing that "equitable considerations can
relax mandatory-joinder requirements when joinder would be unfair"). Preclusion should be a remedy
of last resort. Olds, supra, 150 N.J. at 446-47,
696 A.2d 633. As
the Court recently noted: "[t]he twin pillars of the entire controversy doctrine are
fairness to the parties and fairness to the system of judicial administration." Gelber,
supra, 147 N.J. at 565,
688 A.2d 1044 (citing Joel v. Morrocco,
147 N.J. 546, 555,
688 A.2d 1036 (1997)). In considering fairness to the party
whose claim is sought to be barred, a court must consider whether the
claimant "had a fair and reasonable opportunity to have fully litigated that claim
in the original action." Ibid.
[Id. at 284 (footnote omitted).]
The Appellate Division reversed the trial court and reinstated the complaint against Faridy
and Wagner, concluding that neither the interests of judicial economy nor prejudice to
the defendants justified dismissal. The court observed:
Here, the only issue presented in the lead-solder litigation involved Hillsborough's claim for
damages associated with the plumber's use of lead solder in the drinking water
when the plans, specifications and applicable codes prescribed use of non-lead solder. Allegations
of design defects were not implicated in that complaint at all. The only
allegation against Faridy and Wagner was their alleged negligence in failing to supervise
the plumbers during their installation of piping while using lead solder. Thus, the
claims are clearly separate and discrete. There would be no replication of proofs.
The trial court would not be retracing ground that had already been covered.
Judicial economy will not, therefore, be sacrificed. The fact that the various claims
may have arisen out of the same construction job should not be the
determinative factor.
The policies underlying application of the entire controversy doctrine would not be promoted
by barring the claims under the circumstances presented here. The claims against Faridy,
the architect, and Wagner, the construction manager, were never adjudicated on the merits.
Hillsborough dismissed its claim for negligent supervision of the plumber against Faridy and
Wagner. That disposition resulted in a voluntary stipulation of dismissal with prejudice between
Hillsborough and defendants. However, neither Faridy nor Wagner provided payment or any other
form of consideration for the dismissal. Hillsborough did not exchange any form of
release running in favor of either Faridy or Wagner. Defendants could receive a
"windfall" by being permitted to escape any potential liability for any design defects
because Hillsborough dismissed the claim against them for negligent supervision. The entire controversy
doctrine should not be deployed under the circumstances here to bar Hillsborough's claims,
which were never adjudicated on the merits.
In addition, the unfairness to Hillsborough and to Broscious in not being permitted
to assert its meritorious claims and cross-claims against Faridy and Wagner far outweighs
any prejudice to the parties asserting the preclusion.
Any "unfairness" to Faridy in permitting the claims is questionable. Faridy was the
architect in charge of designing the school, and the school was constructed in
accordance with those designs. There is no evidence that any modifications to the
roof have occurred between 1990 and present. The record does not indicate that
"global settlement" negotiations have commenced. Moreover, Hillsborough, even in the absence of any
earlier filing, could have waited six years before initiating an action against Faridy
and Wagner and still have been within the statute of limitations period. Thus,
there can be no legal prejudice to Faridy for not examining the roof
because Hillsborough could have legally waited up to six years to commence its
lawsuit.
[Id. at 286-87.]
SUPREME COURT OF NEW JERSEY
NO. A-71 SEPTEMBER TERM 2001
ON CERTIFICATION TO Appellate Division, Superior Court
K-LAND CORPORATION NO. 28,
Plaintiff-Appellant,
v.
LANDIS SEWERAGE AUTHORITY,
Defendant-Respondent,
And
BERRYMANS BRANCH, LTD.,
Defendant.
DECIDED July 16, 2002
Chief Justice Poritz PRESIDING
OPINION BY Justice Stein
CONCURRING OPINION BY
DISSENTING OPINION BY
CHECKLIST