Find Laws Find Lawyers Free Legal Forms USA State Laws
Laws-info.com » Cases » South Dakota » Supreme Court » 2004 » DOUBLE DIAMOND CONSTRUCTION v. FARMERS COOPERATIVE ELEVATOR ASSOCIATION and MOLLER CONSTRUCTION, INC., 2004 SD 65
DOUBLE DIAMOND CONSTRUCTION v. FARMERS COOPERATIVE ELEVATOR ASSOCIATION and MOLLER CONSTRUCTION, INC., 2004 SD 65
State: South Dakota
Court: Supreme Court
Docket No: SD 65
Case Date: 05/12/2004
Plaintiff: DOUBLE DIAMOND CONSTRUCTION
Defendant: FARMERS COOPERATIVE ELEVATOR ASSOCIATION and MOLLER CONSTRUCTION, INC., 2004 SD 65
Preview:Unified Judicial System
DOUBLE DIAMOND CONSTRUCTION,
Plaintiff and Appellant,
v.
FARMERS COOPERATIVE ELEVATOR ASSOCIATION OF
BERESFORD, SOUTH DAKOTA, a cooperative corporation; and
MOLLER CONSTRUCTION, INC.,

Defendants and Appellees.

[2004 SD 65]
South Dakota Supreme Court
Appeal from the Circuit Court of
The Second Judicial Circuit
Minnehaha County, South Dakota

Hon. Glen A. Severson, Judge

CHAD W. SWENSON of
Swenson Law Firm
Sioux Falls, South Dakota
Attorneys for plaintiff and appellant.

ROGER W. DAMGAARD and
DANIEL J. HARMELINK of
Sioux Falls , South Dakota
Attorneys for defendants and appellees.

Argued February 18, 2004
Opinion Filed 5/12/2004

#22916
TIMM, Circuit Judge
[¶1.] Double Diamond Construction appeals from the circuit court's vacation of an arbitration award and subsequent judgment confirming an amended award. We affirm.
BACKGROUND
[¶2.] In the spring of 1999, Farmers Cooperative Elevator Association of Beresford (Coop) agreed to purchase a pre-engineered grain storage facility from Moller Construction Company (Moller). The total contract price was $1,355,030, including the cost of construction. Moller subcontracted construction to
Double Diamond Construction (Diamond) for $240,000, with a completion date of August 22. Diamond commenced construction in July, utilizing certain equipment leased from Jerke Construction Company (Jerke).
[¶3.] In the fall of 1999, with harvest underway and the storage facility unfinished, Coop began placing grain in the building. That prompted Diamond to cease work. Diamond informed Moller that the presence of grain in the facility would result in increased construction costs and created risks not covered by insurance. Diamond conditioned return to work upon Coop and Moller providing liability waivers. Moller responded that adequate insurance was the responsibility of the subcontractor and that there was no basis for additional compensation. Moller demanded that Diamond resume work immediately. Diamond refused. Moller then entered the job site and completed construction.
[¶4.] Shortly thereafter, Diamond and Jerke filed mechanic's liens. Diamond claimed it was owed $69,927. Jerke claimed it was owed $34,106.16. Both claims included money owed by Diamond to Jerke
file:///C|/Users/Peter/Desktop/Opinions/12841281.htm[5/8/2013 8:05:08 PM]
Unified Judicial System
for leased equipment. Jerke accepted $29,126.61 from Coop to settle its claim and cancel its lien. In turn, Jerke assigned its claim against Diamond to Coop.
[¶5.] In February 2000 Diamond filed suit against Coop in the United States Federal District Court, District of South Dakota, Southern Division seeking, among other things, to foreclose its mechanic's lien. Coop answered and counterclaimed based on the Jerke assignment. Moller intervened and counterclaimed as well. Moller and Coop shared counsel, although each had initially retained their own. Pursuant to FRCP 26(a)(1)(c), which requires parties to disclose their computation of claimed damages together with documents on which the computation is based, on June 30, 2000, Coop and Moller disclosed: "Defendant, Farmers Cooperative Elevator is not pursuing any damage claim. Moller Construction Company is pursuing a damage claim." The disclosure was not filed. FRCP 5(d). In February 2001 Moller and Coop filed an amended counterclaim. The document included Coop's counterclaim based upon the Jerke assignment.
[¶6.] The case was transferred from the Southern Division in Sioux Falls to the Western Division in Rapid City. Rather than incurring the time and expense involved in litigating the matter in Rapid City, the parties agreed to settle their differences through binding arbitration and dismissed the federal suit.
[¶7.] The arbitration hearing took place on November 20 and 21, 2001. In the course of the hearing, evidence was presented regarding the amount of money owed by Diamond for equipment leased from Jerke. In February 2002 the arbitration award was issued, accompanied by an arbitrator's memorandum and decision. Diamond was to receive $30,519 less $5,513 awarded to Moller on its counterclaim. Coop was awarded nothing. This explanation was given:
It is noted that Defendant Elevator, in its post-hearing memorandum, requests an award of $29,126.61, plus prejudgment interest as it relates to the Jerke Construction claim assigned to it. The Plaintiff has admitted owing Jerke Construction a sum around $21,000, but denying the difference as claimed by Elevator….Defendant Elevator is on record as of June 30, 2000 (Rule 26(a) (1)Voluntary disclosures) as not making any damage claims against Plaintiff. Therefore, the present claim of elevator is denied in all respects.
Coop applied to the arbitrator to modify the award to include a decision on the merits of its claim against Diamond. The arbitrator declined. Coop then applied to the circuit court to vacate the arbitration award on two grounds. First Coop asserted the arbitrator had exceeded his authority and therefore under SDCL 21
Download 12841281.pdf

South Dakota Law

South Dakota State Laws
South Dakota Tax
South Dakota Agencies

Comments

Tips