Find Laws Find Lawyers Free Legal Forms USA State Laws
Laws-info.com » Cases » Texas » 14th District Court of Appeals » 2013 » Guillermo Garza d/b/a Wilhome Builders & Construction v. Jesse CantuAppeal from 164th District Court of Harris County (Opinion )
Guillermo Garza d/b/a Wilhome Builders & Construction v. Jesse CantuAppeal from 164th District Court of Harris County (Opinion )
State: Texas
Court: Texas Northern District Court
Docket No: 14-11-00724-CV
Case Date: 06/11/2013
Plaintiff: Guillermo Garza d/b/a Wilhome Builders & Construction
Defendant: Jesse CantuAppeal from 164th District Court of Harris County (Opinion )
Preview:Reversed and Remanded and Substitute Opinion filed June 11, 2013.

In The

Fourteenth Court of Appeals
NO. 14-11-00724-CV GUILLERMO GARZA D/B/A WILHOME BUILDERS & CONSTRUCTION, Appellant V. JESSE CANTU, Appellee On Appeal from the 164th District Court Harris County, Texas Trial Court Cause No. 2007-36738 SUBSTITUTE OPINION We issued an opinion in this case on April 11, 2013, reversing the trial court's judgment notwithstanding the verdict (JNOV) and remanding for a new trial. Appellee subsequently filed a motion for rehearing. Without changing the disposition of the case, we deny the motion for rehearing, withdraw our previous opinion, and issue this substitute opinion in its place.

Guillermo Garza, doing business as Wilhome Builders and Construction, ("the builder") sued Jesse Cantu ("the buyer") for breach of a construction contract. After the jury returned a verdict for the builder, the buyer moved for JNOV, arguing that the jury's damages calculations lacked evidentiary support. The trial court granted the motion. We conclude that although the damage

amounts found by the jury are not supported by legally sufficient evidence, the builder nonetheless introduced evidence of some amount of damages as defined in the charge. We therefore reverse the trial court's JNOV and remand for a new trial. BACKGROUND The events giving rise to this case are not complicated. The parties agreed in writing that the builder would construct a duplex home for the buyer. When the project was nearly finished, the builder informed the buyer of cost overruns that significantly exceeded the project's estimated price. The buyer refused to pay for these overages or to authorize a final payment of the outstanding portion of the estimated price. The builder sued the buyer, and the jury rendered a verdict in favor of the builder. The issues before us relate primarily to the jury's findings of damages, so we explain the terms of the parties' written contract and the figures at issue in some detail. The parties agreed that the home's price would be "based on cost plus" a 15% "Builder[']s Consulting Fee." In so-called cost-plus contracts like this one, "the contractor is to be reimbursed for costs of materials and labor by the owner and is to receive a stated percentage of such costs as his profit." Burditt v. Sisk, 710 S.W.2d 114, 118 (Tex. App.--Corpus Christi 1986, no writ) (internal

2

quotation marks omitted). Here, the contract's relevant language is as follows:1 Total price of house, including current changes and additions, is as follows .... BASED ON COST PLUS Builders Consulting Fee 15% $31,877.82 Builders Sale Price $244,396.65 Sale Price Per Square Foot $61 Estimates for this job cost are based on and not limited to what the Buyer may choose for his or her customization on this project. The buyer obtained a loan for the $244,396.65 sale price, which represented a total estimated construction cost of $212,518.83, plus a 15% builder's fee of $31,877.82. As the builder completed certain portions of the work on the project, he requested payment from the buyer's lender. The lender would inspect the completed work and release a portion of the authorized funds commensurate with the work accomplished. In this way, the builder received $219,945.75 of the $244,396.65 estimated sale price. Only $24,450.90 of the sale price remained to be paid. As the time for this remaining payment approached, the builder informed the buyer that the project was $55,713.40 over budget. The builder would later testify that these overages resulted from the buyer's selection of materials and from delays early in construction. builder's 15% fee by $8,357.01. The buyer balked at paying the overages, so the builder stopped work and filed a mechanic's lien. Although the home passed the lender's final inspection,
Before beginning construction, the parties reduced the estimated price with an addendum that was to be read with the contract "as if contained therein." The quoted language therefore incorporates the amended price into the initial contract's language. 3
1

The overages made the project's total cost

$268,232.23 instead of the $212,518.83 estimate; this change increased the

the buyer refused to release the final payment of the estimated sale price to the builder. The builder sued the buyer for $88,521.31: the total cost of construction (including overages) plus his 15% fee less the amount already paid. At trial, the parties contested the amount of work remaining when the builder left the project. The buyer argued that considerable work remained and that the builder breached the contract by leaving this work unfinished. The builder testified that "[a] couple punch-out items" remained. The jury found that the buyer breached the contract and that the builder did not. The jury was also asked to find two "elements" of the builder's damages, which we discuss in detail in our analysis below. Each element was submitted to the jury without objection, and each required the jury to determine (among other things) the cost to complete the remaining work. For the first damages element, called "Loss of Contractual profit," the jury awarded $24,450.90--the unpaid portion of the estimated sale price. For the second element, called "Loss of Contractual Profit Plus Expenses Incurred Before Breach," the jury awarded $55,713.40--the amount that the project went over budget. The jury did not award the builder his 15% fee for the overages, so the total jury award was $8,357.01 less than the builder sought. The buyer moved for JNOV, arguing in part that the jury's damages findings were unsupported by the record. The buyer contended, among other things, that the record contained no evidence of the cost to complete the remaining work. Because the jury was told to use this cost in calculating each element of damages, the buyer argued that the jury's findings lacked evidentiary support. The trial court granted the buyer's JNOV motion and rendered a take-nothing judgment. The builder appealed.

4

ANALYSIS I. Standard of review We review a JNOV under a no-evidence standard, meaning we credit evidence favoring the jury verdict if reasonable jurors could and disregard contrary evidence unless reasonable jurors could not. Tanner v. Nationwide Mut. Fire Ins. Co., 289 S.W.3d 828, 830 (Tex. 2009). We will uphold the jury's finding if more than a scintilla of competent evidence supports it. Id. Because there was no objection to the charge submitted, we measure the evidence by the charge as given. See Akin, Gump, Strauss, Hauer & Feld, L.L.P. v. Nat'l Dev. & Research Corp., 299 S.W.3d 106, 112 (Tex. 2009); Osterberg v. Peca, 12 S.W.3d 31, 54
Download 14-11-00724-cv-1.pdf

Texas Law

Texas State Laws
    > Hazelwood Act
    > Texas Statutes
Texas State
    > Texas Cities
    > Texas State
    > Texas Zip Codes
Texas Tax
    > Texas Franchise Tax
    > Texas Sales Tax
    > Texas State Tax
Texas Court
    > Texas Public Records
Texas Labor Laws
    > Minimum Wage in Texas
Texas Agencies
    > Texas DMV
    > Texas Medicaid

Comments

Tips