DO NOT CITE. SEE GR 14.1(a).
Court of Appeals Division I
State of Washington
Opinion Information Sheet
Docket Number: |
65664-3 |
Title of Case: |
Thomas Espinosa, Et Ux., Respondents V. Project Services Corp., Et Ano., Appellants |
File Date: |
01/17/2012 |
SOURCE OF APPEAL
----------------
Appeal from Snohomish Superior Court |
Docket No: | 06-2-11794-6 |
Judgment or order under review |
Date filed: | 06/24/2010 |
Judge signing: | Honorable Ronald X Castleberry |
JUDGES
------
Authored by | Marlin Appelwick |
Concurring: | Ronald Cox |
| J. Robert Leach |
COUNSEL OF RECORD
-----------------
Counsel for Appellant(s) |
| Bryan Craig Gourley |
| Attorney at Law |
| Po Box 1091 |
| Snohomish, WA, 98291-1091 |
Counsel for Respondent(s) |
| Philip Albert Talmadge |
| Talmadge/Fitzpatrick |
| 18010 Southcenter Pkwy |
| Tukwila, WA, 98188-4630 |
|
| Emmelyn Hart |
| Talmadge/Fitzpatrick |
| 18010 Southcenter Pkwy |
| Tukwila, WA, 98188-4630 |
IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
THOMAS ESPINOSA and KARI
ESPINOSA, husband and wife, ) No. 65664-3-I
)
Respondents, ) DIVISION ONE
)
v. UNPUBLISHED OPINION
)
PROJECT SERVICES CORP., a )
Washington corporation; and GREGORY )
GLIEGE, a single man,
)
Appellants. ) FILED: January 17, 2012
)
)
)
)
Appelwick, J. -- Project Services appeals the trial court's February 2010
order affirming specific performance under a vacant land purchase and sale
agreement, extending the closing date and granting the Espinosas attorney fees
and costs. It also argues the Espinosas were not the substantially prevailing
party entitled to fees. Gliege argues that even if the Espinosas were entitled to
fees, they should have been awarded only against Project Services, not against
him personally. Because Gliege was not a party to the original contract, we hold
No. 65664-3-I/2
that he is not personally liable for the judgment of attorney fees and costs. We
affirm in part, reverse in part, and remand for correction of the judgment.
FACTS
The underlying facts of this case were set forth in an earlier appeal to this
court. Espinosa v. Project Servs. Corp., noted at 144 Wn. App. 1025, 2008 WL
1934847, at *2 ("Espinosa I"). Thomas and Kari Espinosa entered into a vacant
land purchase and sale agreement (VLPSA or "the contract") with Project
Services Corporation on March 15, 2006. The VLPSA required Project Services
to maintain the property in the condition it was in when the Espinosas first
viewed it. The VLPSA was originally set to close on May 3, 2006, but the closing
date was extended to May 15, 2006 by agreement of the parties. On May 12,
2006, a fire occurred at the property when debris was brought from off-site and
placed too close to a smoldering fire. Gregory Gliege, the president of Project
Services, extinguished the fire using heavy equipment to cover it with dirt, but
resulting in some alteration to the property. Based on their concerns following
the fire, the Espinosas included a reservation of rights with the closing
documents. Espinosa I, 2008 WL 1934847, at *1-2. Project Services refused to
sign the reservation, and the transaction failed to close. Id. at 2. The Espinosas
brought suit against Project Services on October 13, 2006, requesting specific
performance of the VLPSA and alleging breach of contract, fraud, and
misrepresentation. Id. The trial court granted partial summary judgment for
Project Services and dismissed the Espinosas' claim for specific performance.
Id. at 3. But, in Espinosa I, this court reversed the trial court, holding that the
2
No. 65664-3-I/3
Espinosas had established a prima facie case that the land was improperly
altered by Gliege, and thus there was a question of material fact about which
party breached the contract. Id. at 4.
On October 24, 2008, the Espinosas filed their first amended complaint
adding Gliege as an additional defendant. Project Services had transferred
ownership of the property to Gliege after the closing date, and the Espinosas
named him "so that the relief sought [could] be effectively obtained." The
Espinosas initially sought the remedy of specific performance and damages for
breach of contract. Project Services answered and submitted a counterclaim
against the Espinosas for breach of contract and slander of title. The Espinosas
denied the counterclaim and requested rescission of the contract, or in the
alternative, specific performance if possible.1 They also requested damages.
The Espinosas moved for summary judgment, arguing that Project
Services' failure to maintain the property constituted a material breach of the
contract. Project Services opposed the motion. The trial court granted the
Espinosas' motion in part, finding that Project Services breached its obligations
under the VLPSA. The trial court also found the Espinosas were entitled to
attorney fees and costs. It reserved a determination of the amount of attorney
fees and costs and reserved the issue of the appropriate remedy. The trial court
then bifurcated the trial, with a judge to make the initial decision on liability and
1 The Espinosas contend in their brief that they sought either specific
performance or rescission beginning with their October 2008 first amended
complaint. Project Services disputes this, and it appears that the Espinosas did
not request rescission until their June 19, 2009 answer to Project Services'
counterclaim.
3
No. 65664-3-I/4
determine whether rescission or specific performance was appropriate, and a
jury to determine damages.
Following a bench trial on liability, the trial court issued an oral ruling on
September 3, 2009, finding that Project Services materially breached the
contract and that the Espinosas were entitled to submit the reservation. The trial
court concluded that the Espinosas were entitled to an award of specific
performance, and set the closing date for December 31, 2009. The damages
phase of the trial was set for hearing on December 14, 2009. At the hearing, the
Espinosas stated that they would not present additional evidence on damages.
Instead, they would rely on the evidence already submitted at the liability phase,
would waive their jury trial and defer to the judge's determination. On December
28, 2009, the trial court heard argument on the damages claim and on the
proposed findings of fact and conclusions of law. The trial court announced its
decision awarding no damages to the Espinosas, and entered findings of fact,
conclusions of law, and final judgment that same day. That document confirmed
the change of closing date to December 31, 2009, concluded that the Espinosas
were the prevailing party following Project Services' breach, and concluded that
they did not carry their burden on the matter of damages. The trial court also
awarded the Espinosas attorney fees and costs in the amount of $93,796.62,
after reducing their fees by $7,500 for attorney fees for the damages portion of
the case. Both Project Services and Gliege were named as judgment debtors.
On December 31, 2009, the closing date, the Espinosas' counsel sent an
e-mail to Project Services' counsel stating that the Espinosas would not be
4
No. 65664-3-I/5
closing on the property, and stating that they would release the earnest money
to Project Services.2 The Espinosas later explained to the trial court that they
were unable to close the sale due to difficulty in securing the necessary
financing in light of the economic crisis and more restrictive banking regulations.
Project Services moved for reconsideration and amendment of the
December judgment on January 6, 2010 after the sale again failed to close.
Project Services also sought attorney fees, arguing that based on the failure to
close, the Espinosas breached the contract in their own right and were no longer
the prevailing party. The Espinosas responded that Project Services could not
properly raise an alleged breach of contract as a new claim or theory for
recovery, when that alleged breach occurred three days after the judgment. The
trial court ruled on the motion for reconsideration orally on February 1, 2010,
and in writing on February 23, 2010. The trial court exercised its equitable
authority, pushing the closing date back to April 1, 2010, reaffirming specific
performance as the remedy, and leaving all other contract provisions in effect. It
also modified the original attorney fee award, making it contingent upon whether
the sale actually closed. Under this ruling, the $93,796.62 award was to be
deducted from or credited against the original purchase price in the VLPSA. In
2 The e-mail from the Espinosas' attorney, Rod Dembowski, to Project
Services' attorney, Roy Stegena, read in part as follows:
I received final word late yesterday from the Espinosas that they
will not be closing on the property. Please send whatever form
Preview Properties (assuming they still hold the earnest money)
requires to release the earnest money to your client. We will
promptly have our clients sign it.
5
No. 65664-3-I/6
the event that the Espinosas were again unable close the sale by April 1, 2010,
they would no longer be entitled to the award, and Project Services would
receive the $9,000 earnest money.
While Project Services' January 6, 2010 motion for reconsideration was
pending, Gliege performed additional work on the property, removing trees that
were damaged or fallen, and removing approximately twelve trees to enhance
the property's view. The Espinosas continued to work on obtaining funds to
close the purchase by April 1, 2010. Upon visiting the property shortly before
the new closing date, the Espinosas discovered that Gliege had removed trees
and made additional alterations to the property, such as widening the driveway.
On March 24, 2010, the Espinosas moved the court for relief from
judgment under CR 60 and requested an additional 60 days extension of the
closing to investigate. Gliege and Project Services opposed the motion, arguing
in part that it was untimely. They conceded that Gliege had removed the trees,
but asserted that he did so as maintenance, and to spruce up the property for
sale, believing that the VLPSA had expired when it did not close on December
31, 2009. The trial court conducted a hearing on the motion on March 29, 2010.
At the hearing, the trial court expressed its concern that Gliege and his attorney
failed to disclose these alterations at the February 1, 2010 hearing. The trial
court stated it may have reached a different decision on the motion for
reconsideration if at the time it had been properly informed of the additional
alteration. The trial court granted the Espinosas' motion, permitted the parties to
engage in additional discovery, and extended closing to June 30, 2010. It also
6
No. 65664-3-I/7
emphasized that no additional work was to be done on the property without a
court order.
Discovery commenced, and each side submitted testimony from expert
arborists to address the matter of damages and the value of the removed trees.
The trial court heard the motion on June 22, 2010, and stated:
For the purposes of my ruling, the amount of damages is not
the paramount issue. The issue is, did Mr. Gliege compound the
alteration of the property by the removal of the trees ... . .
. . . .
Had I known what I know now in February when the oral
argument was presented to me, I would not have reconsidered. I
would have [let] the findings of fact, conclusions of law and the
judgment stand.
The trial court made it clear that it would not have chosen specific performance
as a condition of the Espinosas receiving their attorney fees and costs,
essentially requiring them to go through with the purchase, if it was aware of the
additional alteration. The trial court therefore granted the Espinosas' motion to
amend, rescinded the contract, and returned the earnest money to the
Espinosas. It also granted them their attorney fees and costs as it had back in
December, no longer conditioned upon their closing the VLPSA, and added
those additional fees and costs incurred after February. The trial court entered
an amended final judgment consistent with its final order against both Project
Services and Gliege. Project Services and Gliege appealed.
DISCUSSION
When findings of fact and conclusions of law are entered following a
7
No. 65664-3-I/8
bench trial, appellate review is limited to determining whether the findings are
supported by substantial evidence and, if so, whether the findings support the
trial court's conclusions of law and judgment. Sunnyside Valley Irrigation Dist. v.
Dickie, 111 Wn. App. 209, 214, 43 P.3d 1277 (2002), aff'd, 149 Wn.2d 873, 73
P.3d 369 (2003). Evidence is substantial if it is sufficient to persuade a fair-
minded person that the declared premise is true. Id. Conclusions of law are
reviewed de novo. Sunnyside, 149 Wn.2d at 880.
I. February 2010 Order on Reconsideration
Project Services' arguments and assignments of error focus first on the
trial court's February 23, 2010 order on reconsideration. Project Services
contends the trial court erred by upholding the earlier award of attorney fees to
the Espinosas (albeit, conditioned on the closing of the purchase) and by
extending the closing date to April 1, 2010.
A. Attorney Fees and Costs
It is clear from the December 28, 2009 decision that the Espinosas were
the prevailing party on their breach of contract claim, and the trial court initially
awarded them the remedy of specific performance. They also successfully
defended against Project Services' slander of title and breach of contract claims.
The contract provides that the prevailing party is entitled to reasonable attorney
fees and expenses in the event of a suit concerning the agreement. Project
Services now argues that, after failing to close on December 31, 2009, the
Espinosas should no longer have been considered the substantially prevailing
party. On December 28, 2009, the trial court granted the Espinosas the remedy
8
No. 65664-3-I/9
of specific performance. Project Services contends that when the Espinosas
rejected that relief, they breached the contract and relinquished the ability to
claim they were the substantially prevailing party.
Under RCW 4.84.330, "prevailing party" means the party in whose favor
final judgment is rendered. As a general rule, the prevailing party is one who
receives an affirmative judgment in its favor. Riss v. Angel, 131 Wn.2d 612,
633, 934 P.2d 669 (1997). But, if neither party wholly prevails, the determination
of who is the substantially prevailing party depends on the extent of the relief
accorded. Marassi v. Lau, 71 Wn. App. 912, 916, 859 P.2d 605 (1993),
abrogated on other grounds by Wachovia SBA Lending, Inc. v. Kraft, 165 Wn.2d
481, 200 P.3d 683 (2009); Transpac Dev., Inc. v. Young Suk Oh, 132 Wn. App.
212, 217, 130 P.3d 892 (2006).
Project Services relies on Marassi, and asserts that, because it prevailed
in the damages phase of trial, both parties have achieved a measure of success,
and this court must look to the extent of relief accorded. Project Services then
takes this argument even further. It contends that after the Espinosas failed to
close, they had forsaken the only relief afforded to them, leaving Project
Services as the only party entitled to any relief, and thus establishing it as the
substantially prevailing party. We reject that argument. The fact that the
Espinosas were unable to close on December 31, 2009 or avail themselves of
the relief granted does not undermine the trial court's December 28, 2009 ruling
that they were the prevailing party in the underlying lawsuit. Here, unlike in
Marassi, Project Services did not prevail in the underlying contract dispute, but
9
No. 65664-3-I/10
was deemed to have breached the contract and was awarded nothing. Because
the Espinosas succeeded in their breach of contract claim, they were initially,
and remained, the prevailing party.
The trial court considered this same argument on December 28, 2009,
stating:
There are several intertwining issues, but the court would find that
the Espinosas were the prevailing parties under the lawsuit.
And defendants indicate that, well, they should only be
prevailing parties if in fact they carry through with their specific
performance. The court rejects that approach. The court may
have been sitting as a court of equity in terms of presenting various
relief, i.e., rescission or specific performance, but having done so,
the court then is required to follow the conditions of the contract.
And the contract in this case indicates that the prevailing party will
be entitled to their attorneys' fees. It doesn't say, well, you're only
entitled to these attorneys' fees in the event that you in fact close
this transaction. It says, you're entitled to your attorneys' fees if
you are successful at the lawsuit. The plaintiffs have been
successful at the lawsuit.
This analysis remains applicable now. We hold that the trial court did not err in
awarding the Espinosas attorney fees and costs.
B. Extension of Closing Date
In a related argument, Project Services contends the trial court abused its
discretion by extending the closing date from December 31, 2009 to April 1,
2010. Project Services contends that the Espinosas' failure to close by
December 31 constituted a material breach by them as buyers. Project Services
also suggests in the alternative that if the Espinosas did not breach the contract,
it was only the trial court's improper and sua sponte decision to extend the
closing date that prevented such a breach.
10
No. 65664-3-I/11
In matters of equity, trial courts have broad discretionary power to fashion
equitable remedies. Sorenson v. Pyeatt, 158 Wn.2d 523, 531, 146 P.3d 1172
(2006).
The trial court understandably expressed its trepidation with the
Espinosas tying up the property for years if they were not going to go through
with the purchase. While litigation was pending, Project Services was unable to
sell to another buyer. But, the evidence before the trial court in February 2010
suggested the Espinosas had every intention of going through with the specific
performance remedy and always wanted to close the sale. The Espinosas
presented evidence that they attempted to secure financing from Frontier Bank,
but were unsuccessful. Accordingly, the trial court stated:
So it seems to me, using the equitable powers that are
available under this prayer, that it would be appropriate that the
judgment of attorney fees and costs would only be satisfied from
the proceeds of a sale of the property for its original price of
$375,000.
Now, in light of this court's ruling, I will extend by 60 days
the time for the plaintiffs to close, and that is the closing date will
be [April 1], 2010. All other terms of the purchase and sale
agreement shall remain in full force and effect.
This result -- a conditional judgment for fees and costs to the
Espinosas -- ultimately did not stand when the trial court subsequently granted
rescission instead of specific performance in its June 2010 ruling. But, it was a
result that the trial court was entitled to reach, under its broad discretionary
authority sitting in equity. Indeed, as the Espinosas point out, this result was
consistent with what Project Services had in fact requested in its response.
11
No. 65664-3-I/12
Instead of the independently enforceable award of attorney fees and costs that
was in place after the December 28, 2009 judgment, the trial court required the
award of fees and costs to be in the form of an offset against the contract price.
At the time, based on the drastic decrease in property value during the
intervening years, requiring the Espinosas to pay the original 2006 VLPSA price
was a favorable result for Project Services, as they argue themselves. We hold
that the trial court did not abuse its broad discretion in extending the closing
date or conditioning the Espinosas' attorney fees on their closing the sale.
II. Award of Fees Against Gliege Personally
Project Services argues that any fees and costs awarded to the
Espinosas should have been imposed only against Project Services and not
against Gliege personally. It contends that Gliege was not a party to the VLPSA
since the property was not transferred to him until after the material breach had
occurred, but prior to the initiation of the law suit.
Project Services transferred ownership of the property to Gliege by
quitclaim deed on August 8, 2006, several months after the March 2006 fire and
breach of the VLPSA. The Espinosas' original complaint filed on October 13,
2006 only named Project Services. This was consistent with the fact that the
Espinosas and Project Services were the only two parties involved in the
VLPSA. The Espinosas first added Gliege's name in their amended complaint
filed on October 24, 2008. That amended complaint stated: "Defendant Gregory
Gliege was the president of Project Services, caused the property to be
transferred to his personal name after the closing date, and is named herein as
12
No. 65664-3-I/13
the owner of the property in dispute, so that the relief sought can be effectively
obtained." The relief sought was specific performance. It did not allege that
Gliege was a party to the contract.
On September 3, 2009, having already found that Project Services
breached the contract by altering the property, the trial court granted the
Espinosas the remedy of specific performance. The court also concluded that
they were entitled to an award of attorney fees and costs, as provided for in the
contract. The Espinosas filed their motion for attorney fees and costs on
December 16, 2009, and Project Services filed their response on December 22,
2009. Neither party addressed the issue of whether Gliege should be personally
liable, jointly and severally, for any fees or costs awarded. The trial court
awarded the Espinosas a $93,796.62 judgment, and indicated that both Project
Services and Gliege were judgment debtors. That judgment was based on the
fees and costs the Espinosas incurred litigating the breach of contract issue and
damages, which they were entitled to as the prevailing party based on paragraph
p of the VLPSA. But, while the trial court included Gliege as a debtor liable for
the judgment, it did not enter any findings or conclusions pertaining to the basis
for his personal liability.
The matter of Gliege's personal liability on the judgment was raised for
the first time by Gliege and Project Services in their January 6, 2010 motion for
reconsideration. They argued there, as they do now on appeal, that Project
Services was the only seller listed in the VLPSA and that Gliege was never a
party to the contract (or guilty of any breach) in his individual capacity. The
13
No. 65664-3-I/14
Espinosas responded on January 25, 2010 with several arguments for why
Gliege should be personally liable. They contended: (1) that a May 2006
amendment to the VLPSA included Gliege personally; (2) that he was an
assignee of the contract, and took on its obligations and rights when he took
ownership of the property; and (3) that he took title to the property subject to the
Espinosas' contract rights, and the Espinosas' action against him personally was
appropriate since it was an "action on the contract."3 4
The trial court's order on February 23, 2010 made no affirmative findings
of fact on the Espinosas' arguments, nor did it enter any conclusions of law to
support Gliege's personal liability. However, when it added the condition that
the Espinosas were only entitled to attorney fees and costs as an offset upon
closing, the result was that the Espinosas' judgment for fees and costs was
required to come directly out of money they would pay to Project Services in
specific performance upon closing. While Project Services did not own the
property, it was the corporate name on the VLPSA, not Gliege's.
Finally, on the Espinosas' CR 60 motion, the trial court entered an
amended final judgment in June 2010, vacating the February 2010 order and
3 An "action on a contract" is broadly construed and encompasses any
action in which it is alleged that a person is liable on a contract. Herzog
Aluminum Inc. v. Gen. Am. Window Corp., 39 Wn. App. 188, 197, 197, 692 P.2d
867 (1984). An action is "on a contract" if it arises out of the contract and the
contract is central to the dispute. Edmonds v. John L. Scott Real Estate, Inc., 87
Wn. App. 834, 855, 942 P.2d 1072 (1997).
4 They also argued for the first time that liability could be extended to
Gliege by piercing the corporate veil, if the court deemed that appropriate. This
theory was not fully developed and the court entered no findings or conclusions
on this issue.
14
No. 65664-3-I/15
reinstating the independent attorney fee judgment as it initially existed in
December 2009. The trial court also awarded additional fees and costs that had
been incurred since that time. For a third time, the trial court made no findings
of fact or conclusions of law that established Gliege's personal liability.
The burden was on the Espinosas as plaintiffs to demonstrate why they
were entitled to judgment against Gliege personally, when he was not a party to
the original VLPSA at the time of its creation or the time of its breach. See
generally Navlet v. Port of Seattle, 164 Wn.2d 818, 858, 194 P.3d 221 (2008). If
the trial court fails to enter a finding on a material factual issue, this court
presumes that the party with the burden of proof failed to sustain his or her
burden on that issue. State v. Armenta, 134 Wn.2d 1, 14, 948 P.2d 1280 (1997).
Here, the trial court did not enter findings on the matter of Gliege's personal
liability in December 2009, February 2010, or June 2010. Accordingly, we hold
that the Espinosas have failed to sustain their burden of proof that Gliege should
be personally liable for the award of attorney fees and costs. We reverse the
award of judgment against Gliege jointly and severally in his personal capacity,
and affirm the judgment against Project Services.
III. Espinosas' March 24, 2010 CR 60 Motion
While Project Services' January 6, 2010 motion for reconsideration was
pending, Gliege removed additional trees from the property. He did not disclose
this fact to the trial court or the Espinosas at the February 1, 2010 hearing on
Project Services' motion or at any time before the trial court entered the order on
that motion on February 23, 2010. The Espinosas became aware of the
15
No. 65664-3-I/16
additional changes to the property on March 7, 2010, upon visiting to prepare for
the April 1, 2010 closing. On March 24, 2010, the Espinosas moved the court
for relief from judgment under CR 60, requesting an additional 60 day extension
of the closing date to investigate.
A. Challenge to the Timeliness of the Motion
Project Services now argues that the trial court erred by considering and
granting the Espinosas' CR 60 motion because it was untimely. CR 60(b)(3)
allows a court to relieve a party from a final judgment, order, or proceeding
based on "[n]ewly discovered evidence which by due diligence could not have
been discovered in time to move for a new trial under rule [CR] 59(b)." It also
provides that "[t]he motion shall be made within a reasonable time and for [newly
discovered evidence] not more than 1 year after the judgment, order, or
proceeding was entered or taken." CR 60(b). CR 59, in turn, provides that when
there are grounds for a new trial or reconsideration, a motion must be filed not
later than 10 days after the entry of the order. CR 59(b). Project Services
contends that the Espinosas failed to establish that the newly discovered
evidence could not have been discovered within 10 days of the trial court's
February 23, 2010 order.
The trial court heard argument on the CR 60 motion on March 29, 2010.
The court expressed its considerable concern about Gliege and Project
Services' failure to disclose the alterations on February 1, 2010, particularly
since it was prior alterations to the property that initially led to the lawsuit in
2006. And, while the Espinosas' March 24, 2010 motion for relief was not
16
No. 65664-3-I/17
submitted within ten days of the February 23, 2010 order, it was not a motion for
a new trial or for reconsideration, as is contemplated under CR 59(b), and was
thus not subject to the 10 day requirement. Instead, it was a motion for relief
from a judgment or order, governed by CR 60(b). Accordingly, it was required
only to be brought within a reasonable time, not more than 1 year after the order,
and based on "[n]ewly discovered evidence which by due diligence could not
have been discovered in time to move for a new trial under rule [CR] 59(b)." CR
60(b). The VLPSA required the seller to perform no alteration to the land. The
litigation commenced because of an earlier alteration of the land, and Project
Services did not disclose the subsequent alteration during the pendency of the
litigation. The fact that the trial court did not find that the Espinosas failed to
exercise due diligence on these facts is unremarkable and not an abuse of
discretion. We reject the challenge to the trial court's decision to hear the
motion or extend the closing date.
B. Supplemental Award of Attorneys Fees
The trial court allowed discovery, heard the merits of the motion for relief
in June. It reversed its February 2010 order, which had the effect of reinstating
the prior judgment from December 2009. The trial court also awarded the
Espinosas attorneys fees incurred subsequent to the entry of the February
order.
Project Services challenges the award of those fees. However, there is
no doubt that the Espinosas were the prevailing party and that the proceedings
between February and June were a continuation of the same cause of action on
17
No. 65664-3-I/18
the contract. As previously noted, the contract provides for the award of fees to
the prevailing party. The Espinosas prevailed under the December judgment
and under the June order which reinstated it. We find no error.
IV. Contested Findings of Fact and Conclusions of Law
Finally, Project Services assigns error to two of the trial court's findings of
fact and one conclusion of law contained in the December 28, 2009 findings of
fact, conclusions of law, and final judgment. The disputed findings of fact read:
16. The Espinosas contacted Defendants about their
concerns. The VLPSA provided for a ten day extension of closing.
Project Services Corp. refused to delay closing to allow the
Espinosas time to investigate the nature and extent of the damage
to the Property.
. . . .
18. The Espinosas were within their rights by executing a
Reservation of Rights with respect to the damages caused by the
fire and grading and entering the document into escrow.
And, the disputed conclusion of law reads:
8. Plaintiffs were within their rights in terms of presenting
Exhibit No. 4 (the reservation of rights document) and it was not a
breach of the contract for them to do so.
Project Services contends that if the court finds in their favor on this matter, all
other assignments of error become moot.
Project Services does not raise an argument that substantial evidence
does not support the disputed findings or that the findings do not support the
conclusion. Instead, it argues that when the Espinosas added the reservation of
rights to the VLPSA in 2006 upon discovering the alteration to the property, it
prevented the transaction from closing by adding new material contract terms.
18
No. 65664-3-I/19
But, as the Espinosas point out, this is merely a resurrection of the same
argument that was raised in, and resolved by, this court in Espinosa I. In
Espinosa I, this court stated:
Through the reservation of rights the Espinosas sought to ensure
that they received the land they had contracted to buy in the
condition they bargained for. The reservation was an attempt to
preserve existing rights under the contract rather than assert new
rights or responsibilities for the parties. However, adding a
reservation of rights in the absence of breach by Project Services
would itself be a breach by Espinosa, and they would be ineligible
for specific performance.
Espinosa I, 2008 WL 1934847, at *3. Project Services never sought further
review of this court's determination in Espinosa I. The earlier holding thus
constitutes the law of the case. See Lutheran Day Care v. Snohomish County,
119 Wn.2d 91, 113, 829 P.2d 746 (1992) ("'law of the case'" refers to "'the
binding effect of determinations made by the appellate court on further
proceedings in the trial court on remand.'") (footnote omitted) (quoting 15 L.
Orland & K. Tegland, Washington Practice: Judgments § 380, at 56 (4th ed.
1986)). While this language found only that there was a material fact still in
dispute and that summary judgment for Project Services was inappropriate, it
now must be read in conjunction with the subsequent undisputed trial court
finding that Project Services did indeed breach the contract by altering the
property. The reservation of rights was not an assertion of new rights, but was
merely the Espinosas' attempt to preserve their already existing rights under the
VLPSA. The trial court simply abided by the decision in Espinosa I in entering
the challenged findings and conclusion. We reject Project Services' argument.
19
No. 65664-3-I/20
V. Attorney Fees
Both parties seek attorney fees and costs on appeal under RAP 18.1.
The contract provides for the award of attorney fees and costs to the prevailing
party:
Attorneys' Fees. If Buyer or Seller institutes suit against the other
concerning this Agreement, the prevailing party is entitled to
reasonable attorneys' fees and expenses.
Because the Espinosas substantially prevail on appeal, we award them attorney
fees and costs as against Project Services. However, Gliege has prevailed on
the issue of his personal liability for attorneys fees. Inasmuch as that claim was
based on the assertion of contractual liability for those fees, Gliege is entitled to
attorneys fees attributable to that issue on appeal. See Herzog Aluminum, Inc.
v. Gen. Am. Window Corp., 39 Wn. App. 188, 197, 692 P.2d 867 (1984).
We affirm in part, reverse in part, and remand for correction of the
judgment.
WE CONCUR:
20
No. 65664-3-I/21
21
|