Universal Equipment Co. v. State By and Through Dept. of Environmental Quality
1992 WY 136
839 P.2d 967
Case Number: 92-21
Decided: 10/21/1992
Supreme Court of Wyoming
UNIVERSAL EQUIPMENT CO., an Ohio corporation, Appellant (Defendant),
v.
STATE of
Wyoming By and
Through the DEPARTMENT OF ENVIRONMENTAL QUALITY, Appellee
(Defendant).
Appeal from
District Court, Fremont County, Elizabeth A. Kail,
J.
David D. Freudenthal of Herschler,
Freudenthal, Salzburg, Bonds & Rideout, P.C., Cheyenne, and Michael K.
Yarbrough of Frost and Jacobs, Columbus, Ohio, for appellant.
Joseph B. Meyer, Atty. Gen., Mary
B. Guthrie, Steve Jones, Sr. Asst. Attys. Gen., Thomas A. Roan, Asst. Atty.
Gen., and Joel M. Vincent of Vincent & Vincent, Riverton, for appellee.
Before MACY, C.J., and THOMAS, CARDINE,
URBIGKIT* and GOLDEN,
JJ.
* Chief Justice at time of oral
argument.
MACY, Chief
Justice.
[1.] Appellant Universal
Equipment Co. challenges the district court's order requiring it to post an
additional performance bond to ensure reclamation of its mine-site buildings and
facilities. Appellant contends that the Wyoming Environmental Quality Act (WEQA)
does not authorize the Department of Environmental Quality (DEQ) to impose
reclamation and bonding requirements for buildings and facilities which were
built before the WEQA was enacted.
[2.] We
affirm.
[3.] Appellant raises the
following issues:
1. Whether buildings
and facilities that existed within a mine permit under the Open Cut [Land]
Reclamation Act of 1969 are subject to additional reclamation and bonding
requirements under the Environmental Quality Act of 1973 by virtue of converting
the original permit to a permit under the EQA of 1973.
2. Whether entry of an
order by the District Court directing the payment of reclamation bond proceeds
pursuant to a contract which authorized such payments only upon the completion
of all reclamation, precluded the Court from later determining that reclamation
was not complete and directing the posting of additional
bond.
[4.] Appellee State of Wyoming restates the issues
as:
I. Whether the
district court correctly determined that buildings and structures at the
Atlantic City Mine are subject to the reclamation and bonding requirements of
the Wyoming Environmental Quality Act.
II. Whether the district court has
determined that reclamation at the Atlantic City mine is
complete.
[5.] United States Steel
Corporation owned and operated an iron ore mine located near Atlantic City in
Fremont County, Wyoming, for many years, first pursuant to a permit issued under
the authority of the Open Cut Land Reclamation Act and then, starting in
November 1974, under the authority of a WEQA permit. After receiving its WEQA
permit, United States Steel continued to operate the mine for several more years
until it finally ceased active mining in 1983. Rather than reclaim the mine
itself, United States Steel sold the mine and transferred its mining permit to
Appellant in January 1985. By accepting the transfer of United States Steel's
mining permit, Appellant obtained salvage rights to the on-site mining equipment
and materials and assumed responsibility for reclaiming the mine site. As part
of the permit transfer, Appellant was required to submit a new reclamation plan
and to post a reclamation performance bond of slightly more than $1.8
million.
[6.] Beginning in 1985,
Appellant contracted with various companies to perform different aspects of the
reclamation project, such as engineering and construction. Reclamation
activities continued from 1985 until the spring of 1989, when a dispute arose
between one of these companies, ARIX Corporation, and Appellant regarding
Appellant's failure to pay ARIX for its engineering services. ARIX filed a
breach-of-contract action, naming both Appellant and the State of Wyoming, by and through
the DEQ, as defendants.
[7.] ARIX moved for, and the
district court granted, a summary judgment against Appellant for unpaid
engineering services. To satisfy its judgment, ARIX applied for a writ of
postjudgment garnishment against Appellant's reclamation performance bond being
held by the DEQ. The State resisted ARIX's motion for a postjudgment
garnishment, contending that it could not allow garnishment of the bond until
additional reclamation had been completed. In conjunction with its answer
resisting a postjudgment garnishment, the State petitioned the district court
for a declaratory judgment to determine the responsibilities between the three
parties and, of particular importance to this appeal, to determine Appellant's
obligation to demolish or make some acceptable use of the mine's buildings and
facilities as part of its reclamation effort.
[8.] ARIX filed a motion
requesting the court to separate its garnishment action from the DEQ's petition
for a declaratory judgment. The district court granted ARIX's motion to separate
and, in an order entered on May 21, 1990, found that the funds held by the DEQ
were not subject to garnishment. In that same order, the district court found
that a contract existed between the DEQ and Appellant regarding Appellant's
performance bond. The court based its conclusion that a contract existed upon a
series of letters exchanged between Appellant and the DEQ in which Appellant
agreed to convert its $300,0001 reclamation bond from an
irrevocable letter of credit to cash and to release the funds to the State
subject to specific conditions. Appellant's release of the funds was expressly
conditioned upon the State using the money, first, to pay for any remaining
engineering and construction work done on the reclamation project; second, to
pay any amounts owing on construction services; third, to pay ARIX for
engineering services; and, finally, to return any excess funds to Appellant. The
district court specifically enforced that part of the contract which required
the DEQ to pay the amount owed by Appellant to ARIX for engineering
services.
[9.] On April 27, 1990, the
court held a hearing on the DEQ's petition for a declaratory judgment, with the
significant issue being whether the DEQ could require Appellant to post a
sufficient performance bond to ensure the costs of demolishing and removing the
mine's buildings and facilities. In a declaratory judgment and order for a
reclamation performance bond, the district court found that the DEQ could
require Appellant to provide additional bonding for Appellant's remaining
reclamation obligations, including demolition of the on-site structures. The
court ordered Appellant to submit a detailed plan within sixty days, indicating
which buildings it intended to demolish and the proposed future use for those
buildings it intended to retain, or, in the alternative, to post a $4 million
reclamation performance bond with the DEQ. Under either option, the order
required that a bond of approximately $386,000 be posted to ensure revegetation
of the land which had not been reclaimed as well as certain less costly
contingency items, such as repairing drainage structures and dust control.
However, if Appellant chose to post the $4 million bond, the $386,000 would be
included in the $4 million.
[10.]
The DEQ's method of estimating the costs of demolishing the mine's
buildings was less than precise. Mark Moxley, a district supervisor for the
DEQ's Land Quality Division, testified that he reached an estimate of
Appellant's demolition costs by averaging the costs of demolishing the buildings
on five trona mining operations with comparably sized structures. Mr. Moxley
felt that his estimate of $3 million was within "20 or 30 percent" of the actual
costs of demolishing the buildings at the mine site. In its order requiring
Appellant to either post a $4 million bond2 or propose a beneficial use for any
retained buildings, the court acknowledged Appellant's contention that some of
the reclamation costs were unnecessarily high. To accommodate Appellant's
objections, the court granted Appellant sixty days to provide a detailed cost
analysis showing that the actual reclamation costs would be lower than those
estimated by the DEQ.
[11.]
Appellant's response to the court's order claimed that any obligations
concerning the buildings were controlled by its permit and reclamation plan,
neither of which required it to demolish the buildings. Although Appellant felt
that it had no obligation to demolish the buildings, it still conformed to the
court's request to demonstrate an acceptable postmining use for the buildings.
Appellant described the present use of the buildings as essentially being
storage space for mining machinery waiting to be sold. Rather than using the
buildings in the future, Appellant hoped to sell the property, including the
buildings and facilities. Appellant declined the court's invitation to submit an
analysis showing that the DEQ's building demolition estimates were inaccurate.
Instead, Appellant relied upon its argument, now repeated on appeal, that the
district court was precluded from ordering an additional bond to be posted. The
district court found that Appellant's proposed future use for the buildings was
insufficient and ordered Appellant to post a $4 million
bond.
[12.]
The first issue we must consider is whether the WEQA and its rules and
regulations grant the DEQ authority to impose reclamation and bonding
requirements upon mine-site buildings which were built prior to the WEQA's
enactment. Appellant contends that the WEQA's language is prospective, thus
precluding the DEQ from imposing reclamation and bonding requirements on
pre-WEQA facilities. As evidence that the WEQA is prospective, Appellant quotes
Wyo. Stat. 35-11-406(b) (Supp. 1992), which provides in pertinent part: "The
[mining permit] application shall include a mining plan and reclamation plan
dealing with the extent to which the mining operation will disturb or change the
lands to be affected." (Emphasis added.)
[13.]
As with any statute, our primary consideration is discerning the
Legislature's intent. Belle Fourche Pipeline Company v. State, 766 P.2d 537, 542
(Wyo. 1988).
Although this Court has not construed the particular mine reclamation provisions
at issue in this case, we have previously interpreted other sections of the
WEQA. People v. Platte Pipe Line Company, 649 P.2d 208 (Wyo. 1982). In Platte
Pipe Line Company, we noted that, as an environmental statute designed to
protect the public, the WEQA is entitled to receive a liberal construction.
Id. at 212 (citing Woolley v. State Highway
Commission, 387 P.2d 667, 673 (Wyo. 1963)). A liberal construction does not
mean that we can force words out of their natural meaning but does permit us to
give words a fair and reasonable interpretation so as to obtain the object for
which the statute was designed. Soles v. State, 809 P.2d 772, 774 (Wyo.
1991).
[14.]
To better understand whether the WEQA even applies to pre-WEQA buildings
and facilities, it is helpful to first briefly examine the Open Cut Land
Reclamation Act (Reclamation Act), which governed surface mining reclamation
prior to the WEQA's enactment. 1969 Wyo. Sess. Laws ch. 192, 1-14. In 1969, the
Legislature enacted the Reclamation Act as a means of curbing economic and
environmental damage caused by surface mining in Wyoming. Under the Reclamation Act, surface
mining operators were required to obtain a mining permit and to post a bond with
the Commissioner of Public Lands to ensure the availability of sufficient funds
for the reclamation of affected lands. The Reclamation Act also established
obligations for surface mining operators to reclaim and restore the land, but it
was criticized as being vague and having inadequate reclamation standards. Its
ineffectiveness ultimately led to its repeal by the Legislature in 1973. 1973
Wyo. Sess.
Laws ch. 250, 3. Belle Fourche Pipeline Company, 766 P.2d at 546. See also
Robert E. Brown, Comment, Land Quality: The Regulation of Surface Mining
Reclamation in Wyoming, 9 LAND & WATER L.REV. 97, 107
(1974).
[15.]
Repeal of the Reclamation Act did not mean that lands disturbed by
open-cut mining could be left unreclaimed. Rather, the Legislature expanded and
clarified the reclamation and conservation duties of surface mining operators by
enacting the WEQA. 1973 Wyo. Sess. Laws ch. 250, 1. In addition to
establishing a new permitting and reclamation scheme, the WEQA contained several
provisions which helped existing surface mining operators bridge the gap between
the Reclamation Act and the WEQA. These provisions for existing mining
operations provide us with valuable assistance in understanding whether the
WEQA's reclamation requirements apply to preexisting operations or, as Appellant
claims, to only operations conducted after the WEQA's enactment. Among those
provisions is Wyo. Stat. 35-11-401 (Supp. 1992), which provides in pertinent
part:
(a) No mining
operation or operation by which solid minerals are intended to be extracted from
the earth shall be commenced after the effective date of the act, except in
accordance with its requirements. It is recognized these measures are performed
in the public interest and constitute an expense to the operator, and while this act applies to all mining
operations, no operator shall be compelled to perform at his own expense
measures required under this act with respect to operations that were completed
or substantially completed prior to the effective date of this act. . .
.
(b) All surface or
underground mining operations operating at the date of enactment of this statute
shall have a period of one (1) year within which to fulfill the requirements of
this act. This period may be extended at the discretion of the council if the
administrator has been unable to review and evaluate all operations that are
presently operating under a permit issued by the state land commissioner in
compliance with the "Open Cut Land Reclamation Act of
1969[."]
(Emphasis
added.)
[16.]
The obvious inference to be drawn from subsection (a) is that those
preexisting operations not completed or substantially completed were subject to
the WEQA's requirements. Operation is defined in Wyo. Stat. 35-11-103(e)(viii)
(Supp. 1992):
(viii) "Operation"
means all of the activities, equipment, premises, facilities, structures, roads, rights-of-way, waste
and refuse areas excluding uranium mill tailings and mill facilities, within the
Nuclear Regulatory Commission license area, storage and processing areas, and
shipping areas used in the process of excavating or removing overburden and
minerals from the affected land or for removing overburden for the purpose of
determining the location, quality or quantity of a natural mineral deposit or
for the reclamation of affected lands[.]
(Emphasis added.) In this case, the
facilities and structures were constructed prior to the WEQA's enactment, but
the operation as a whole was not completed or substantially completed prior to
the WEQA's effective date, July 1, 1973. United States Steel operated the mine
prior to the WEQA's enactment and continued to actively mine iron ore at the
site until 1983. Since the buildings were part of the mining operation and the
operation was not completed or substantially completed prior to the WEQA's
effective date, we conclude that the buildings are subject to the WEQA's
requirements.
[17.]
Section 35-11-401(b)'s one-year grace period merely reinforces the idea
that the WEQA applies to preexisting operations. It would be illogical to grant
operators a grace period for complying with the WEQA if the WEQA applied only to
operations conducted after its enactment. The purpose of a grace period is,
presumably, to temper the severity of adapting to new requirements. If the WEQA
only applied to prospective mining operations, existing operators would be in
the same position as new operators and would have no need for a grace
period.
[18.]
Appellant does not really contest the WEQA's application to pre-WEQA
operations but argues that the WEQA's reclamation and bonding requirements are
prospective even if other WEQA aspects may apply. Appellant's interpretation
appears to contradict the very purpose of the WEQA. The WEQA is designed to
"enable the state to prevent, reduce and eliminate pollution; to preserve, and
enhance the air, water and reclaim the land of Wyoming; to plan the development, use,
reclamation, preservation and enhancement of the air, land and water resources
of the state." Wyo. Stat. 35-11-102 (1988). If we adopt
Appellant's interpretation of the WEQA as not requiring reclamation of
preexisting operations, Appellant could leave the buildings as empty shells if
it so desired. Such a result would be inconsistent with the Legislature's stated
intent to either reclaim or develop the land.
[19.]
In addition to the general statutory purpose language, the WEQA contains
specific evidence of the Legislature's intent to apply the reclamation
requirements to preexisting operations which were not completed or substantially
completed prior to its enactment. Wyo. Stat. 35-11-402(a)(vii) (Supp. 1991)3 provided:
(a) The council shall,
upon recommendation by the advisory board, establish rules and regulations
pursuant to the following reclamation standards for the affected areas,
including but not limited to:
. . . .
(vii) In administering
established rules and regulations on such standards the administrator and
advisory board shall consider all the facts and circumstances bearing upon any
reclamation plan. In consideration of reclamation plans for any mining operation
that is presently being conducted in the state under a permit issued by the
state land commission under the "Open Cut Land Reclamation Act of 1969[,"]
particular attention shall be paid to:
(A) The social and
economic value of the product mined;
(B) The technological
availability for economic feasibility of reclaiming the affected
area[.]
[20.]
Section 35-11-402(a)(vii) fully indicated that the Legislature intended
to require reclamation of some preexisting operations. When considering a
reclamation plan for an operation presently being conducted under a Reclamation
Act permit, the administrator must pay particular attention to certain social,
economic, and technological variables. This added attention is paid only to
reclamation plans submitted by Reclamation Act permittees. It would be illogical
to make special concessions for those reclamation plans which concern operations
being conducted after the WEQA's enactment. Presumably, the added considerations
in 35-11-402(a)(vii) were meant to reduce the harshness of complying with the
WEQA's new reclamation requirements. If the reclamation plans referenced in
35-11-402(a)(vii) did not apply to preexisting operations and applied only to
new operations, no need to grant special consideration to Reclamation Act
permittees would exist because the reclamation burdens would be the same as
those of any new operator. Section 35-11-402(a)(vii)'s language reinforced this
interpretation. That paragraph discussed the reclamation plan for any mining
operation "presently being conducted" and the economic feasibility of reclaiming
the "affected area." Both phrases apply to operations already in existence at
the time the WEQA was enacted.
[21.]
Appellant also argues that the WEQA's bonding provisions provide evidence
that the WEQA is not applicable to preexisting facilities. The WEQA's primary
bonding provision is Wyo. Stat. 35-11-417 (Supp. 1992), which provides in
pertinent part:
(a) The purpose of any
bond required to be filed with the administrator by the operator shall be to
assure that the operator shall faithfully perform all requirements of this act
and comply with all rules and regulations of the board made in accordance with
the provisions of this act.
. . . .
(c) The amount of any
bond to be filed with the administrator prior to commencing any mining shall
be:
(i) For an initial
bond the amount equal to the estimated cost of reclaiming the affected land
disturbed and restoring, as defined in W.S. 35-11-103(f)(iii), any groundwater
disturbed by in situ mining during the first year of operation under each
permit. . ..
(ii) For renewal bonds
the amount equal to the estimated cost of reclaiming the land to be disturbed
during the renewal period, and the estimated cost of completing reclamation of
unreleased lands and groundwater disturbed during prior periods of time. The
estimated cost shall be based on the operator's cost estimate, which shall
include any changes in the actual or estimated cost of reclamation of unreleased
affected lands, plus the administrator's estimate of the additional cost to the
state of bringing in personnel and equipment should the operator fail or the
site be abandoned.
[22.]
Other bonding provisions include Wyo. Stat. 35-11-403(a)(ii) (Supp.
1992) which authorizes the Land Quality Division's administrator "[t]o fix the
amount of, collect, maintain and otherwise comply with the statutory performance
bond requirement set out in W.S. 35-11-417." See also Wyo. Stat.
35-11-110(a)(ii) (Supp. 1992).
[23.]
In our view, both 35-11-403(a)(ii) and 35-11-417(c)(ii) authorize the
administrator to require a bond to ensure the reclamation of pre-WEQA buildings
and facilities. As Appellant accurately points out, the statute does not refer
to determining a bond amount on the basis of the costs of demolishing buildings
which predate the WEQA. However, to be consistent with the rest of the WEQA, the
broad statutory language must be read as allowing such a bond to be required.
The WEQA clearly contemplated the reclamation of those operations not completed
or substantially completed prior to the WEQA's enactment. If the WEQA were
designed, at least in part, to reclaim preexisting operations, that goal would
be severely impeded by the lack of a bonding requirement. Performance bonds
provide an incentive for operators to complete reclamation and also provide
financing for reclamation costs in forfeiture cases. Essentially, the bonding
requirement is what makes the reclamation system work, so it would have been
incongruous for the Legislature to require reclamation but not bonding for
pre-WEQA operations.
[24.]
Having determined that the WEQA's reclamation and bonding requirements
apply to preexisting operations, we must now examine the duty imposed by the
WEQA upon operators to reclaim their buildings and structures. The WEQA's sole
reference to buildings is in 35-11-406(b)(iv), which requires the reclamation
plan to include the "[m]ethod of disposal of buildings and structures erected
during the operation." The Land Quality Division's rules and regulations offer
further insight into what an operator is required to do with mine-site buildings
and structures. Prior to September 1986, the rules and regulations stated in
pertinent part:
b. In addition to that
information required by W.S. 35-11-406(b), each application for a mining permit
shall contain:
. . . .
(3) A plan whereby the
operator will reclaim the affected lands to the proposed postmining land use in
accordance with Chapter IV, Section 2a. which shall
include:
. . . .
(h) A plan for the
disposal of buildings and structures in accordance with the requirements of
Chapter IV, Section 2.k.
Chapter II, Section 2.b(3)(h)
(1985).
k. Disposal of buildings and
structures.
(1) All buildings and
structures must be removed or dismantled unless it can be demonstrated to the
administrator's satisfaction that the buildings or structures will be of
beneficial use in accomplishing the proposed use of the land after reclamation
or for environmental monitoring.
Chapter IV, Section 2.k(1) (1985).
The rules and regulations regarding disposal of buildings were modified in
September 1986 to require that mining permit applications
include:
(H) A plan for the
disposal of buildings and structures erected, used or modified by the
applicant in accordance with the requirements of Chapter IV, Section
2.(k).
Chapter II, Section 2(b)(iii)(H)
(1986) (emphasis added).
(k) Disposal of buildings and
structures.
(i) All buildings and
structures constructed, used or
improved by the operator must be removed or dismantled unless it can be
demonstrated to the administrator's satisfaction that the buildings or
structures will be of beneficial use in accomplishing the proposed use of the
land after reclamation or for environmental monitoring.
Chapter IV, Section 2(k)(i) (1986)
(emphasis added).
[25.]
Some dispute between the parties exists concerning which version of the
rules and regulations applies. In its brief, the State relies upon the more
recent language, while Appellant contends that the older language should apply.
The newer language is applicable to all mining operations "commenced or
conducted" after the effective date of the rules and regulations. Chapter I,
Section 3(a) (1986). Since active mining ceased in 1983, the determination of
which version applies depends upon whether Appellant's reclamation efforts
constitute mining operations. We perceive no need to decide this question
because, pursuant to either version of the rules and regulations, mine operators
are required to remove or dismantle the buildings unless they will be put to a
beneficial use consistent with the proposed use of the land. The language added
in 1986 merely limits the buildings which must be dismantled, a concept which
would appear, if anything, to potentially benefit, not hinder, Appellant. Thus,
we conclude that the WEQA, as supplemented by the Land Quality Division's rules
and regulations, requires Appellant to either reclaim the buildings or put them
to a beneficial use.
[26.]
The only question remaining is whether Appellant could be required to
post a bond for the buildings' demolition if the DEQ consistently approved
reclamation plans for the mine site which did not require the operator to remove
or demolish the buildings. Appellant maintains that, by excluding reclamation
and removal of the buildings from the bond and the reclamation plans between
1973 and 1989, the DEQ demonstrated its long-standing interpretation of the WEQA
as not requiring pre-WEQA buildings to be reclaimed. Appellant urges this Court
to defer to the agency's long-standing interpretation. WYMO Fuels, Inc. v.
Edwards, 723 P.2d 1230, 1237 (Wyo. 1986). Contrary to Appellant's claim, we
do not think that the DEQ interpreted the statute as excluding reclamation and
bonding requirements for the buildings. Instead, we detect a pattern of
carelessness by the DEQ in approving reclamation plans which did not
specifically state what would be done with the buildings once mining
ceased.
[27.]
United States Steel, Appellant's predecessor, only briefly mentioned the
mine's buildings in its first reclamation plan submitted in
1974:
The buildings
associated with operations are all located on fee ground owned by U.S. Steel and
are of substantial construction. It is possible that beneficial use can be made
of these buildings following completion of operations. Those buildings for which
there is no beneficial use will be dismantled and salvaged. Since buildings and
ground are both owned by United States Steel, final disposition decisions should
remain with United States Steel.
When Appellant acquired the mine in
1985, the DEQ required a new reclamation plan as a condition of the permit
transfer. In November 1985, Appellant complied with the DEQ's condition by
submitting a proposed reclamation plan which identified certain buildings to be
removed and others to remain. Appellant subsequently submitted a proposed permit
revision application and reclamation plan which suggested disposing of the
buildings in the same manner as the first plan but added: "The use of the
facilities to remain has not yet been determined." Appellant's final, approved
reclamation plan dealt with the buildings by proposing to "[m]aintain [the
facilities] as is for future commercial/industrial use." An internal DEQ
memorandum written to the file said: "The mine facilities area will be left
intact in hopes of serving a future industrial or commercial
use."
[28.]
The trial court found that Appellant's approved reclamation plan assumed
that the buildings remaining in the permit area would not be demolished but
instead would be put to commercial use. We agree with the trial court's
assessment. Both United States Steel's and Appellant's reclamation plans
indicated an intent to put the buildings to future beneficial use. The internal
memorandum evidences the DEQ's belief that the buildings would be put to a
beneficial postmining use and that they did not need to be reclaimed. Thus, we
conclude that the DEQ's long-standing failure to include the costs of building
demolition in the mine's bonding and reclamation requirements was due to an
assumption that the buildings would be put to beneficial use, not that the
buildings did not have to be reclaimed.
[29.]
We recognize the perception that it is manifestly unfair for the DEQ to
require a reclamation bond of approximately $1.8 million, to reduce that bond to
$300,000 after Appellant partially reclaimed the mine, and then to increase the
bond to $4 million. The perception of injustice is not entirely accurate. After
the DEQ became concerned that Appellant might abandon the mine's buildings, the
DEQ sought a declaratory judgment to determine Appellant's obligation to reclaim
the buildings or put them to a beneficial use. The court's declaratory judgment
allowed Appellant to remove the buildings from the WEQA's reclamation and
bonding provisions by providing a detailed plan for the buildings' future use.
Appellant did not provide an adequate plan explaining the buildings' future use.
The failure to supply an adequate plan meant that Appellant was required to post
a $4 million bond. A $4 million bond appears inequitable especially in light of
Mr. Moxley's testimony that his estimate was within "20 or 30 percent" of the
actual demolition costs; i.e., perhaps a million dollars off. Although $4
million is obviously somewhat speculative, the court's declaratory judgment
stated: "[Appellant] has the right to initially establish the amount of the
reclamation performance bond by competent engineering analysis, the report of
which is subject to review and approval by the Land Quality Administrator."
Appellant chose not to submit a proposed bond amount. Even though we may be
frustrated by the high bonding requirement, it was Appellant's responsibility to
provide the court with a more accurate estimate, and it chose not to provide
such an estimate.
[30.]
In its second issue, Appellant contends that the district court was
precluded from determining that reclamation at the mine was not complete.
Appellant's argument is related to ARIX's summary judgment against Appellant for
engineering services. After obtaining its summary judgment against Appellant,
ARIX sought to garnish Appellant's reclamation bond being held by the DEQ. The
district court found that the bond was not subject to garnishment. However, the
court did find that a contract existed between the DEQ and Appellant regarding
Appellant's reclamation bond and that, pursuant to the contract, the DEQ was
required to pay ARIX the amount owed to it by Appellant. The contract between
the DEQ and Appellant consisted of a series of letters between the two in which
Appellant agreed to convert the form of its reclamation bond from an irrevocable
letter of credit to cash and to release the funds to the DEQ subject to certain
conditions. Among the conditions was the proviso that the DEQ would pay ARIX for
engineering services only after it paid the costs of any remaining reclamation
work. The district court ordered the DEQ to specifically perform that part of
the contract which required that ARIX be paid the money owed to it by Appellant.
Appellant now argues that, by ordering the payment of the past due amounts to
ARIX, the trial court must necessarily have found that all reclamation had been
completed because ARIX was to be paid only after all reclamation was
completed.
[31.]
Appellant's argument is inconsistent with the trial court's subsequent
declaratory judgment, in which the court stated:
By its Order for
Specific Performance of Contract dated May 21, 1990, by which the [DEQ] was
ordered to pay $99,201.85 to ARIX Corporation (the project engineer) to complete
payment for its engineering services, the Court did not make findings regarding
the obligations of [Appellant] for final reclamation of the Atlantic City Iron
Mine as governed by Permit to Mine Number 231C; instead, the Court reserved such
determinations for further order in this case.
Consistent with the foregoing
finding, the court required Appellant to post a bond to ensure the completion of
several additional items, such as revegetation and drainage control. The
combination of the court's specific statement regarding Appellant's reclamation
obligations and its order for Appellant to post a bond for additional
reclamation leads to the inescapable conclusion that the court's order for
specific performance was not a determination that all reclamation had been
completed.
[32.]
In a related argument, Appellant claims that, pursuant to the doctrine of
equitable estoppel, the DEQ is estopped from requesting any additional
reclamation activity. Appellant's argument for invoking the doctrine of
equitable estoppel is twofold: First, the DEQ consistently represented to
Appellant that the $300,000 bond would be sufficient to complete all remaining
reclamation activities. Appellant relied upon this representation when it
changed its irrevocable letter of credit to cash and gave the funds to the DEQ.
Second, when the district court ordered the DEQ to pay ARIX, it necessarily
determined that all reclamation activities had been completed. According to
Appellant, the DEQ's failure to appeal the district court's order represented to
Appellant that all reclamation activities had been completed and that the DEQ
should now be estopped from asserting otherwise.
[33.]
To support its claim of equitable estoppel against the DEQ, Appellant
relies upon this Court's statement in Seaman v. Big Horn Canal Association, 29
Wyo. 391, 398, 213 P. 938 (1923): "[O]ne who by his acts or representations
intentionally or through culpable negligence induces another to believe certain
facts to exist, and the latter, not knowing the facts, acts on such belief to
his substantial prejudice, the former is, in equity, estopped to deny the
existence of such fact." In more recent cases, we have said that equitable
estoppel requires some misrepresentation and is generally applied to prevent
fraud, either constructive or actual. B & W Glass, Inc. v. Weather Shield
Mfg., Inc., 829 P.2d 809, 813 (Wyo. 1992);
Squaw Mountain Cattle Company v. Bowen, 804 P.2d 1292, 1297 (Wyo. 1991). Equitable
estoppel against a governmental agency requires even more egregious
conduct.
Equitable estoppel
should not be invoked against a government or public agency functioning in its
governmental capacity, except in rare and unusual circumstances and may not be
invoked where it would serve to defeat the effective operation of a policy
adopted to protect the public.
Big Piney Oil & Gas Company v.
Wyoming Oil and Gas Conservation Commission, 715 P.2d 557, 560 (Wyo. 1986),
quoted in State ex rel. Wyoming Workers' Compensation Division v. Rivera, 796
P.2d 447, 450 (Wyo. 1990), and in Sare v. Sheridan County Board of County
Commissioners, 784 P.2d 593, 595 (Wyo. 1989).
[34.]
In this case, the DEQ was functioning within its governmental capacity of
ensuring the mine's reclamation. We discern no rare and unusual circumstances
which support invoking equitable estoppel against the DEQ. When the DEQ reduced
Appellant's reclamation bond to $300,000, it obviously considered that amount as
being sufficient to complete the remaining reclamation requirements at the mine.
In the ensuing letters between Appellant and the DEQ in which Appellant agreed
to release its funds to the DEQ, both parties assumed that $300,000 would
satisfy the additional reclamation costs. We can find no evidence in the record,
and Appellant offers no evidence, to indicate that the DEQ misrepresented the
reclamation costs.
[35.]
Appellant's second ground for equitable estoppel is that, by not
appealing the trial court's order for specific performance, the DEQ represented
to Appellant that all reclamation activities had been completed. Appellant's
contention that the DEQ's failure to appeal constituted a representation to
Appellant seems tenuous at best and certainly does not give rise to grounds for
equitable estoppel.
[36.]
Affirmed.
FOOTNOTES
1 As
previously noted, Appellant posted a bond of approximately $1.8 million when it
received United States Steel's mining permit. At the time ARIX filed its
complaint, the DEQ had reduced Appellant's bond to $300.000 in recognition of
Appellant's partial reclamation of the mine site.
2 Apparently, the $4 million figure
was composed of the $3 million for demolition costs plus other additional
reclamation work and a fifteen percent contingency fee to cover site security
and unforeseen expenses.
3 Amended by 1992 Wyo. Sess. Laws ch. 60,
3 effective April 1, 1992.
URBIGKIT, Justice, concurring in part and
dissenting in part.
[37.]
It is recognized that stream pollution problems are potentially involved
in this appeal. In consideration of the present partial performance status of
the reclamation activities, forcefully discussed in current news reports, the
need for urgency in our appellate decision is apparent.
[38.]
In recognizing that need, I concur with the court's decision in general
direction, but dissent in part with concern that we ask for the impossible
which, if true, will not be achieved. I also dissent because no proper basis is
presented to require the bond at the amount stated for building removal and
structure site renovation or that a bond should presently be required to remove
the structures constituting office and processing
facilities.
[39.]
It seems completely clear that a use for the buildings has been
considered and may probably be pursued by a reasonably early date. Under that
circumstance, a punitive bond in the amount provided is not justified by
anything found in the Department of Environmental Quality rules, regulations or
executed agreements entered into by the department with either the predecessor,
United States Steel Corporation, or the present appellant. There is a punitive,
perspective imposition, unexpectedly created, for this major cost responsibility
to appellant. Hercules Powder Co. v. State Bd. of Equalization, 66 Wyo. 268, 208 P.2d 1096
(1949). See also People v. Platte Pipe Line Co., 649 P.2d 208 (Wyo.
1982).
[40.]
I generally agree with the direction of the decision that appellant
retains a reclamation maintenance responsibility for areas of dams, ponds and
other facilities originally involved in mining where stream damage may occur
from moisture flow. The $386,000 bond for revegetation and other restorative
activities is justified, but I would not go further to require the total bond of
$4 million. If we do, it is as likely as not that even a $386,000 bond will be
an unrealistic expectation.
[41.]
I join in affirming the decision of the trial court, except with the
administrative agency's increase of the reclamation bond to a sufficient total
covering the cost of building demolition and site renovation. It is concluded
that the additional imposition by the agency is unauthorized, Roberts Const. Co.
v. Vondriska, 547 P.2d 1171 (Wyo. 1976), and this court's decision in
approval cannot be factually and legally supported in this appellate record.
Platte Pipe Line Co., 649 P.2d 208; Holding's Little America v. Board of County
Com'rs of Laramie County, 670 P.2d 699 (Wyo. 1983), appeal after remand 712 P.2d
331 (Wyo. 1985); Rocky Mountain Oil and Gas Ass'n v. State Bd. of Equalization,
749 P.2d 221 (Wyo. 1987).
[42.]
Consequently, I concur in the requirement for the general reclamation
bond and dissent to the additional inclusion of the building structure
demolition and site renovation costs.
Citationizer Summary of Documents Citing This Document
Cite | Name | Level | |
---|---|---|---|
Wyoming Supreme Court Cases | |||
Cite | Name | Level | |
1997 WY 12, 932 P.2d 734, | Griess v. Office of the Atty. Gen., Div. of Criminal Investigation | Cited | |
2004 WY 153, 101 P.3d 465, | BELL v. SCHELL | Cited |
Cite | Name | Level | |
---|---|---|---|
Wyoming Supreme Court Cases | |||
Cite | Name | Level | |
1923 WY 18, 213 P. 938, 29 Wyo. 391, | Seaman v. Big Horn Canal Ass'n | Cited | |
1949 WY 22, 208 P.2d 1096, 66 Wyo. 268, | Hercules Powder Co. v. State Bd. of Equalization | Cited | |
1963 WY 65, 387 P.2d 667, | Woolley v. State Highway Commission | Cited | |
1976 WY 20, 547 P.2d 1171, | Roberts Const. Co. v. Vondriska | Cited | |
1982 WY 88, 649 P.2d 208, | People v. Platte Pipe Line Co. | Discussed at Length | |
1983 WY 105, 670 P.2d 699, | Holding's Little America v. Board of County Com'rs of Laramie County | Cited | |
1985 WY 207, 712 P.2d 331, | Holding's Little America v. Board of County Com'rs of Laramie County | Cited | |
1986 WY 69, 715 P.2d 557, | Big Piney Oil & Gas Co. v. Wyoming Oil and Gas Conservation Com'n | Cited | |
1986 WY 161, 723 P.2d 1230, | WYMO Fuels, Inc. v. Edwards | Cited | |
1987 WY 186, 749 P.2d 221, | Rocky Mountain Oil and Gas Ass'n v. State Bd. of Equalization, | Cited | |
1988 WY 158, 766 P.2d 537, | Belle Fourche Pipeline Co. v. State | Cited | |
1989 WY 222, 784 P.2d 593, | KEITH SARE v. SHERIDAN COUNTY BOARD OF COUNTY COMMISSIONERS | Cited | |
1992 WY 38, 829 P.2d 809, | B & W Glass, Inc. v. Weather Shield Mfg., Inc. | Cited | |
1991 WY 12, 804 P.2d 1292, | Squaw Mountain Cattle Co. v. Bowen | Cited | |
1991 WY 51, 809 P.2d 772, | Soles v. State | Cited |