Weston County Hosp. Joint Powers Bd. v. Westates Const. Co
1992 WY 150
841 P.2d 841
Case Number: 90-99
Decided: 11/20/1992
Supreme Court of Wyoming
WESTON COUNTY HOSPITAL JOINT POWERS BOARD, Appellant (Plaintiff),
v.
WESTATES
CONSTRUCTION COMPANY, Appellee (Defendant).
Appeal from District Court of
Laramie County, Nicholas G. Kalokathis,
J.
Raymond B.
Hunkins, Jones, Jones, Vines & Hunkins, Wheatland, for appellant.
Joseph
E. Hallock, Banks, Johnson, Wolfe & Hallock, Gillette, and John J. Delaney,
Banks, Johnson, Johnson, Colbath & Huffman, Rapid City, S.D., for appellee.
Before
MACY, C.J., and THOMAS, CARDINE,
URBIGKIT* and GOLDEN,
JJ.
* Chief Justice at time of oral
argument.
THOMAS, Justice.
[1.] The set of questions
that the court must determine in resolving this appeal is:
1.
Whether a joint powers board, created pursuant to the provisions of the Wyoming
Joint Powers Act, Wyo. Stat. 16-1-102 to -109 (1990), is a "political
subdivision" as to which the requirements of Article 16, Section 7 of the
Constitution of the State of Wyoming must be met before a bill, claim, account
or demand can be audited, allowed, or paid?
2.
Whether a joint powers board is a "governmental entity" so that a claimant must
satisfy the provisions of Wyo. Stat. 1-39-113 (1988)?
3.
Whether, assuming that a joint powers board is a "political subdivision" or a
"governmental entity," the record demonstrates satisfaction of the
constitutional or statutory requirements?
The
trial court ruled that the joint powers board was not a "political subdivision;"
there had been no violation of the provisions of Wyo. Stat. 1-39-113 (1988)
because the conduct of arbitration proceedings was a condition precedent to the
accrual of any claim; the requirements of 1-39-113 were substantially
satisfied; and the award of the arbitrators should be confirmed. Consistently
with the trial court, we hold that a joint powers board is not a "political
subdivision;" a joint powers board is a "governmental entity" and the provisions
of 1-39-113 must be satisfied; in the circumstances of this case in which the
action was instituted by the joint powers board, a waiver of compliance with the
notice requirements must be acknowledged; and the award of the arbitrators
appropriately and correctly was confirmed. We affirm the decision of the trial
court.
[2.] Weston County Hospital
Joint Powers Board (Board), as appellant, frames these issues for this
appeal:
I.
Whether the district court had jurisdiction to confirm an arbitration award on a
claim against a Wyoming governmental entity where the claimant
neglected and refused to comply with the requisite procedures mandated by the
Wyoming Constitution and the Wyoming Governmental Claims
Act?
II.
Whether the district court erred in confirming an arbitration award against a
Wyoming public
entity where the claimant failed to provide documentation sufficient for the
public entity to examine the claim by means of a constitutionally contemplated
and court-ordered audit?
III.
Whether the district court erred in confirming an arbitration award which
contained manifest mistakes of, and disregard for, Wyoming law, resulting in
an award which exceeded the arbitration panel's powers?
IV.
Whether the district court erred in failing to modify the arbitration award to
incorporate the installment payment provisions of the Wyoming Governmental
Claims Act?
Westates
Construction Company (Westates), as appellee and the defendant in the court
below, sets forth this statement of the issues:
I.
Whether the district court had jurisdiction to confirm an arbitration award in
favor of a contractor and against a joint powers board?
A.
Whether compliance with Article 16, Section 7, of the Wyoming Constitution,
pertaining to political subdivisions, is a prerequisite to the arbitration of a
contractor's claim against a hospital joint powers board?
B.
Whether the 1984 Wyoming Governmental Claims Act, W.S. 1-39-101, et seq.,
prohibits arbitration of damage claims between a contractor and a joint powers
board even though contract documents prepared by the joint powers board require
arbitration to resolve such claims?
C.
Whether Westates' claims were timely filed?
II.
Whether the district court erred in confirming the arbitration
award?
III.
Whether the district court erred in refusing to modify the award to incorporate
the installment provisions of the Governmental Claims Act?
[3.] The Board was created
pursuant to the provisions of the Wyoming Joint Powers Act, Wyo. Stat.
16-1-102 to -109 (1990), by the towns of Upton
and Newcastle together with Weston County. There is no dispute that these
three entities all are "political subdivisions." Westates, a privately owned
Wyoming corporation, in August of 1984, entered into an agreement with the Board
pursuant to which Westates was to construct a public hospital in Newcastle. The
contract, which was drafted by the Board, provided that Westates was to pursue
any and all disputes arising from the contract through arbitration proceedings
before being allowed access to the courts.
[4.] The hospital
construction project was substantially completed in May of 1986 and, in October
of that year, Westates sought additional compensation of $682,369.59. Westates
presented its claim for this amount in an unverified and unsigned letter that
was sent by its attorney to a member of the Board. The claim for additional
compensation was refused, and Westates, pursuant to the agreement, sought
arbitration through the American Arbitration Association.
[5.] Within a short time,
the Board filed an action in the district court seeking to quash further
proceedings. The Board contended that the provisions of the Wyoming Governmental
Claims Act, Wyo. Stat. 1-39-101 to -120 (1988), inhibited the enforcement of
the arbitration clause incorporated in the contract. The district court, after
considering the arguments of the parties, ruled that the Wyoming Governmental
Claims Act did not prevent enforcement of the arbitration clause and that
arbitration was appropriate under the circumstances. The Board appealed that
ruling to this court, but its appeal was dismissed in June of 1988 on the ground
that the order of the district court was not a final order, as defined in
Wyo.R.App.P. 1.05.
[6.] After dismissal of its
appeal, the Board requested an audit of Westates' records. When Westates
refused, the Board filed an "Application for Order Authorizing Conduct of an
Audit" in the district court. The district court, in accordance with the
stipulation presented by the parties, incorporated that request into an order,
and the Board's independent auditor accomplished the audit. The end result of
the audit was that all but $4,000 of the additional compensation demanded by
Westates was rejected.
[7.] The arbitration
proceedings were conducted in February and May of 1989. After its case-in-chief
was completed, Westates presented a revised, and diminished, summary of its
claim so as to conform it to the evidence. Immediately following the Board's
argument in the arbitration proceedings, Westates adjusted the claim once again.
The final product of the arbitration was an award of $99,905 in favor of
Westates. Promptly thereafter, Westates filed its "Motion for Order Confirming
Arbitration Award" with the district court. The Board, sometime later, filed its
"Application to Vacate, Modify or Correct Arbitration Award." On March 1, 1990,
the district court, after ruling that the Board was not a "political
subdivision" and that Westates' claim first accrued when the American
Arbitration Association entered its award, denied the Board's motion. The court
entered a judgment for Westates in the amount determined by the arbitration. The
Board has appealed from that order.
[8.] The major premise for
the Board's argument is found in its contention that the district court was
without jurisdiction to rule in the case because Westates had not followed the
process established by Wyo. Const. art. 16, 7 as it was required to do.
Article 16, Section 7 of the Constitution of the State of Wyoming provides as
follows:
Payment of public
money.
No money shall be paid
out of the state treasury except upon appropriation by law and on warrant drawn
by the proper officer, and no bills, claims, accounts or demands against the state, or any county or political
subdivision, shall be audited, allowed or paid until a full itemized
statement in writing, certified to under penalty of perjury, shall be filed with
the officer or officers whose duty it may be to audit the same (emphasis
added).
Concretely,
the Board asserts that Westates had a duty to present a "full itemized statement
in writing, certified to under penalty of perjury," to the Board's officer or
officers, whose duty it was to audit the same in accordance with the
requirements of Wyo. Const. art. 16, 7, before proceeding to arbitration. The
Board then contends that Westates is now foreclosed from any remedy by the
inherent statute of limitations found in 1-39-113, because more than two years
have passed since the hospital project was completed, and no such document has
been presented. Cf. Dee v. Laramie
County, 666 P.2d 957 (Wyo. 1983) (court lacks
jurisdiction in action against government entity when no claim has been filed
pursuant to 1-39-113). The Board couples to this argument a contention that
the only effective forum in which Westates could have pursued its rejected claim
was the district court of the Sixth Judicial District in and for Weston County,
and that any resolution offered by virtue of the arbitration proceedings was
inefficacious because the arbitration award was confirmed by a court lacking
jurisdiction. The concomitant of this argument is that the arbitration clause
included in the contract, even though it was fully complied with, is not binding
upon the Board.
[9.] The Board was
established pursuant to the Wyoming Joint Powers Act, Wyo. Stat. 16-1-102 to
-109 (1990), and, being neither the State nor a county, the Board must be a
"political subdivision" in order to insist upon compliance with the requirements
of the constitution. If the Board is not a "political subdivision," it must
defend the confirmation of the arbitration upon some alternative
ground.
[10.] The criteria for identifying a "political
subdivision" are found in Witzenburger v. State ex rel. Wyoming Community
Development Authority, 575 P.2d 1100, reh'rg denied, 577 P.2d 1386 (Wyo. 1978).
There, we concluded that a "`political subdivision' must be an entity of the
same kind or class as a county, city, township, town or school district,"
Witzenburger, 575 P.2d at 1112, and that it would be characterized by certain
distinctive badges including a prescribed geographic area, a requirement for
having officers duly elected by the inhabitants of that area at a public
election, and a legal power to levy and collect taxes. Witzenburger. This is
still the applicable test. While the list we have recited is not all-inclusive,
any "body politic" not possessing at least these three basic attributes cannot
be a "political subdivision." See Witzenburger.
[11.] After examining the Wyoming Joint Powers
Act, we find that two of the Witzenburger criteria clearly cannot be ascribed to
the Board. First: The Board will have no elected officials. All its members,
including any member who may be assigned the role of an officer, must be
appointed by the governing bodies of the participating agencies. Wyo. Stat. 16-1-106(a),
(b). In this instance, the participating agencies are the towns of Upton and Newcastle and
Weston
County. Second: The Board
has no independent power to tax. Wyo. Stat. 16-1-107. Further, although not
proscribed by the Wyoming Joint Powers Act as are the other two requisite
criteria, the record does not demonstrate any specific territorial or geographic
boundaries within which the Board is contained or has the authority to function.
Wyo. Stat.
16-1-101 to -109.
[12.] We hold that the Board does not comply
with even the threshold criteria for identification as a "political
subdivision," as articulated in Witzenburger, and we need not review the claims
of the Board concerning the constitutional demands and Westates' alleged failure
to meet those requirements. Wyo.Const. art. 16, 7 does not apply in this
instance. The Board's argument that the district court lacked jurisdiction
because of the failure to comply with those constitutional mandates, including
those requiring itemization and certification under penalty of perjury, is
without merit since the Board is not a "political
subdivision."
[13.] The Board offers an alternative argument
for identifying it as a "political subdivision." It cites Frank v. City of Cody,
572 P.2d 1106 (Wyo. 1977), for the proposition, which certainly is sound, that
nothing prohibits existing "political subdivisions from joining together as
allowed by the Joint Powers Act." The argument the Board advances is that any
such aggregate of "political subdivisions" inherently must be recognized as a
"political subdivision." This sophisticated argument is an application of the
adage that "the whole is equal to the sum of its parts." In addition, the
further contention is that any separate body, board, or agency created by
another entity or entities must be for all intents and purposes essentially the
same as the entity or entities out of which it is formed. The conclusion then
asserted is that the Board, no matter how it is formed, must be perceived as
possessed of the cumulative powers, rights, and constitutional or statutory
protection available to any of its individual constituents. Stated another way,
the Board argues that any claim or demand directed to the Board is a claim or
demand addressed to its participating agencies, of which one is a county and the
other two are political subdivisions.
[14.] The fallacy in this contention is the
assumption that, by the creation of a joint powers board, the participating
entities in some manner merge so as to form a body that is essentially the
equivalent of their individual identities. This is not the case. The
participating entities, whatever they may be, do not merge. Instead, they simply
agree to create and support a different and independently managed organization
that exists and functions for their mutual benefit. In doing so, they do not
surrender or delegate any of their individual rights and
prerogatives.
[15.] In advancing this theory, the Board
apparently ignores the fact that many, if not most, special purpose governmental
agencies or bodies, such as the Board, are created specifically to establish a
separate organization that, for whatever reasons, is independent of its
participants. These new entities function to pool resources and establish a
buffer isolating the participating entities. It follows that an attack on the
new body is not an attack on the participating entities and, consequently, the
only protections or powers it may need, or legally has, are those specifically
identified in its enabling statute and other controlling authorities. The very
existence of the Joint Powers Act, which defines a discrete entity that is
independent of the participating entities, supports this resolution and is
contrary to the contention of the Board. We hold that an independent "special
purpose" body or unit created through an arrangement between other governmental
entities, like a joint powers board, does not assume the collective
characteristics, or the rights and responsibilities of the individual
participants. A joint powers board is what the Wyoming Joint Powers Act, and
other controlling authority, say it is, without more. It is not an entity that
is possessed of the collective characteristics and powers of those entities that
created it. A "governmental entity" that is formed by a coalition of "political
subdivisions" is not another "political subdivision," unless it somehow is
possessed of the criteria identified in Witzenburger. Perhaps this point is
sufficiently emphasized by noting that Westates, in apparent recognition of this
distinction, sought its remedy, not from the towns of Upton and Newcastle and
Weston
County which were the
participating entities, but from the Board itself.
[16.] Another suggestion offered by the Board,
is that a "governmental entity" and a "political subdivision" are equivalent
concepts. Possibly, this contention is suggested by 1-39-103(a)(i) and (ii).
The first subparagraph defines governmental entities to include the State, the
University of
Wyoming, and any local
government. The second subparagraph defines local government and includes joint
powers boards, as well as all political subdivisions of the state among the
numerous bodies identified. It is clear that, using the broad definition of a
governmental entity, any political subdivision is a governmental entity. The
inverse, however, is not true and a governmental entity does not necessarily
constitute a political subdivision. Perhaps the best demonstration of that
verity is that it would be unnecessary to include "political subdivision" in the
definition of 1-39-103(a)(ii) if any governmental entity were a political
subdivision. A conclusion such as that suggested with respect to the
qualification of a governmental entity as a political subdivision would rob the
rationale of this court in Witzenburger of any efficacy.
[17.] We turn then to the argument that
Westates was required to comply with the Wyoming Governmental Claims Act since
the Board clearly is a governmental entity within the definition found in
1-39-103(a)(i). The Constitution of the State of Wyoming provides that no suit may be
maintained against either the state or its various governmental components,
including any and all "governmental entities," without the consent and direction
of the legislature. Wyo.Const. art. 1, 8; Worthington v. State, 598 P.2d 796 (Wyo. 1979); Retail Clerks Local 187 AFL-CIO v.
University of Wyoming, 531 P.2d 884 (1975); Hjorth Royalty Company
v. Trustees of University of
Wyoming, 30 Wyo. 309, 222 P. 9
(1924). Such consent must be formalized by statute, the mechanism by which our
legislature articulates policy. Worthington. In 1979, the legislature adopted
the Wyoming Governmental Claims Act, which permits suits against the state if
certain explicitly stated conditions have been complied with. Wyo. Stat. 1-39-102(a).
Because this statute abrogates common law, it is to be strictly construed.
Reliance Insurance Company v. Chevron,
U.S.A., Inc., 713 P.2d 766
(Wyo.
1986).
[18.] The argument of the Board on this issue,
focusing upon 1-39-113, is that Westates' claim accrued in May of 1986, when
the hospital construction project had been substantially completed, and it
follows that any claim made by Westates should have been presented within two
years of that date. Claims presented subsequent to the cut-off date, the Board
argues, are a nullity and of no effect. The district court ruled to the
contrary, relying upon the agreement entered into by the parties. It held that
no claim existed in this instance until the results of the arbitration, a
contractual condition precedent, demonstrated either an entitlement or rejection
of Westates' claim. We agree with the ruling of the district court. See Westates
Construction Company v. City of Cheyenne, 775
P.2d 502 (Wyo. 1989); Brasel & Sims
Construction Company v. State
Highway Commission, 655 P.2d 265 (Wyo.
1982).
[19.] The pertinent statute provides, in part,
as follows:
Claims procedure.
(a) No action shall be
brought under this act against a governmental entity unless the claim upon which
the action is based is presented to the entity as an itemized statement in
writing within two (2) years of the date of the alleged act, error or omission,
except that a cause of action may be instituted not more than two (2) years
after discovery of the alleged act, error or omission, if the claimant can
establish that the alleged act, error or omission was:
(i) Not
reasonably discoverable within a two (2) year period; or
(ii)
The claimant failed to discover the alleged act, error or omission within the
two (2) year period despite the exercise of due diligence.
Wyo. Stat. 1-39-113
(Supp. 1992).
Neither
this provision nor any other provision of the Wyoming Governmental Claims Act
prohibits or encourages arbitration as a device for resolving disputes between
governmental entities and those parties with whom they contract or otherwise do
business. See Hot Springs School District No. 1
v. Strube Construction Company, 715 P.2d 540 (Wyo. 1986); American National Bank of Denver v. Cheyenne Housing
Authority, 562 P.2d 1017 (Wyo. 1977). Although not explicitly mentioned
in the statute, "[a]rbitration is favored by public policy in this court,"
Hot Springs, 715
P.2d at 547, since it does provide a means for inexpensive and expeditious
resolution of various claims and controversies without the need for resort to a
formal tribunal and its rigid adherence to rules of law. Jackson State Bank v.
Homar, 837 P.2d 1081 (Wyo. 1992); Hot Springs; T & M Properties v. ZVFK Architects and
Planners, 661 P.2d 1040 (Wyo. 1983); Matter of
Town of Greybull, 560 P.2d 1172 (Wyo. 1977). Consistently,
our predilection, especially when the parties have agreed to arbitration as they
did in this case, is to uphold the results of arbitration if we can determine
any legal or equitable way so to do. Northern Supply; Oil, Chemical & Atomic
Workers Union, Local 2-230 v. Great Lakes
Carbon Corporation, 376 P.2d 640 (Wyo. 1962).
[20.] Ultimately, as the district court wisely
perceived, resolution of this issue hinges completely upon the date when
Westates' claim accrued. If it accrued in May of 1986, as the Board contends, it
is untimely, and it is not in a form prescribed by the statute. The result
should be dismissal as a matter of law. See Dee, 666 P.2d 957. On the other hand, if the Westates'
claim first accrued upon completion of the arbitration proceedings in May of
1989, Westates' filing would be timely, and the only remaining concern would be
questions with respect to the form of the claim. The claim is found in this
record in the motion to confirm arbitration presented to the district court, and
the question would be whether that motion manifests sufficient compliance with
the Act under the unique circumstances of this case.
[21.] We conclude that the Wyoming Governmental
Claims Act, although providing the exclusive means for resolving existing claims
against government entities, does not serve to negate contractual provisions
moving toward a similar goal. We hold that the best, and perhaps the only, way
to reconcile these provisions is to regard a claim against a governmental entity
as not having accrued until all contractual terms creating a condition precedent
have been exhausted, as the district court did. See Westates. Then, and not
before, the explicit directives of the Wyoming Governmental Claims Act will
control. Consequently, we hold that Westates' claim against the Board accrued
upon completion of the arbitration in May of 1989.
[22.] Our resolution of this issue also
responds to the contention of the Board that the case was not heard in a proper
forum since, by the district court's confirmation of arbitration, the
controversy actually was resolved in the district court subsequent to the
compliance by the parties with the contractual condition specifying arbitration.
The district court, contrary to the arguments of the Board, did have
jurisdiction over the matter because Westates' claim was filed in a timely
manner. In so holding, we recognize, and we agree with the Board, that the
American Arbitration Association lacks jurisdiction to enter a binding award
against a governmental entity. See Wyo. Stat. 1-36-101 to -119 (1988). For
that reason, it was essential that Westates seek confirmation of the award from
the district court as it did. The lack of authority on the part of the
arbitrators to enter a binding award had no effect on the jurisdiction of the
district court. The claim was properly presented by Westates' motion, and the
district court had the power to rule.
[23.] As we have indicated, the necessity of a
claim raises the question whether Westates' motion to confirm arbitration, filed
by it in the district court, was a sufficient claim in the format required by
the statute to procedurally comply with the Wyoming Governmental Claims Act. If
it was not, even though Westates' motion was timely, the district court still
would be without jurisdiction to rule on it. The district court, after
considering the issue, concluded that Westates' motion sufficiently complied
with the statutory requirements. We agree with this
ruling.
[24.] The statute requires that an accrued
claim must be presented to the governmental entity as an itemized statement in
writing. Wyo.
Stat. 1-39-113. Normally, the proper procedure for the presentation of such a
claim would be to first submit the arbitration results to the Board for
satisfaction, instead of immediately seeking relief directly from the district
court. In most instances, a failure to proceed in this manner, that is
presenting the arbitration result as a claim in accordance with the statutes,
could be fatal to any remedy. This case is different, however, because the Board
initiated this action in the district court well before Westates' claim had
accrued, and the Board then participated in the arbitration proceedings. Since
this case is different from the normal one, we agree that the Board, by its
actions in the lower court, waived its right to any procedural defenses
regarding notice that it otherwise normally could assert.
[25.] In so deciding, we hold that the Board
had adequate notice of the claim and that the law does not require Westates, or
any other claimant similarly situated, to engage in the futile act of providing
further documentation under such circumstances. A contrary result would indeed
elevate form over substance. Westates sufficiently complied with the
Governmental Claims Act under the circumstances of this case. We add a caveat to
the members of the Wyoming Bar, however. Our holding in this case is not to be
broadly construed as an invitation to avoid strict adherence to the terms of the
Wyoming Governmental Claims Act. In this regard, we also recognize that
Westates' unverified and unsigned letter to a member of the Board would have
complied with the statute, which simply requires the presentation to the entity
of an itemized statement in writing, had there been an accrued claim at the time
that the letter was submitted to the member of the Board.
[26.] In its second issue, the Board questions
the action of the district court in confirming an arbitration award where
Westates failed to provide documentation sufficient to allow the Board to
examine the claim by means of a "constitutionally contemplated and court-ordered
audit." We fail to discern the relevance of this issue or how it might affect
the outcome of this appeal. We already have tested the constitutional
applications of Wyo.Const. art. 16, 7, holding that they do not apply in this
case. We would be remiss if we then endeavored to stretch those requirements to
encompass concerns over the district court's order with respect to an audit.
Even if we assume that the record would support Westates' alleged failure in
this regard, the Board does not cite authority nor provide cogent legal argument
to explain why such a failure would justify either a reversal or any other
remedy in this case. Lacking such assistance, we conclude we should not consider
the matter further. See Dynan v. Rocky Mountain Federal Savings & Loan, 792
P.2d 631 (Wyo. 1990); Burg v. Ruby Drilling
Co., 783 P.2d 144 (Wyo. 1989).
[27.] The district court based its award on its
confirmation of the results of the arbitration, not on the results of any audit.
This renders the audit of little consequence, as the Board had ample opportunity
to contest the accuracy of Westates' claim in the course of the arbitration
proceedings. In addition, the proper procedure for the Board to have followed,
if it was not satisfied with Westates' submission of documents, was a motion to
compel in the district court. The record demonstrates no such motion, and we
will not entertain this matter which is raised for the first time on appeal.
Matter of Estate of McCue, 776 P.2d 742 (Wyo.
1989); ABC Builders, Inc. v. Phillips, 632 P.2d 925 (Wyo. 1981); Merritt v. Merritt, 586 P.2d 550 (Wyo.
1978).
[28.] The foregoing resolution of the first two
issues asserted by the Board makes it unnecessary for us to address separately
the Board's third issue. The question raised there, in its broadest form, is
whether the district court erred in confirming an award that contained manifest
errors of Wyoming law and exceeded the power of the
arbitration panel. As we have set forth in our discussion, we do not find the
errors of law alluded to, and the question of whether the panel of the American
Arbitration Association acted in excess of its powers is of no consequence
because it was the district court, not the arbitration panel, that actually
entered the order awarding compensation in this case. In addition, it is clear
that Westates adequately complied with the Wyoming Governmental Claims Act,
notwithstanding the contrary contentions offered by the
Board.
[29.] The final issue asserted by the Board
concerns the failure of the district court to modify the results of the
arbitration so as to incorporate the "payment by installment" provisions of the
Governmental Claims Act. In its decision letter, the district court did not
address this issue directly and, instead, entered judgment for immediate payment
of the entire amount of the award. The Board asserts that this must be error.
The pertinent statutory provision is:
(c) In addition to the
procurement of insurance under subsection (b) of this section a local
governmental entity may:
* * * *
* *
(iv) Pay the judgment
or settlement, with interest thereon, in not to exceed ten (10) annual
installments in cases of undue hardship and levy not to exceed one (1) mill per
year on the assessed value of the governmental entity for such purpose * *
*."
Wyo. Stat.
1-39-118(c)(iv) (1988).
[30.] The essential argument by the Board in
its brief is that the statute creates an option for the governmental entity
pursuant to which, at its election, it may proceed to satisfy a judgment
rendered against it in annual installments. The Board then notes the following
testimony from its treasurer and chief fiscal officer and asserts its claim of
hardship is justified by the testimony:
That it
would be an undue hardship on the Weston County Hospital Joint Powers Board to
pay any judgment, but that the hardship would be substantially lessened if the
Joint Powers Board were permitted to pay any judgment in ten annual payments as
provided for in 1-39-118.
The
Board contends that this court, because the statutory conditions allegedly had
been met and the Board is electing to exercise its option, should order payment
of the judgment in ten annual payments, although with interest to Westates. We
do not agree with this contention.
[31.] The issue of annual payments was
presented to the district court, and the result of that presentation was that
the district court responded by awarding the amount in full to Westates. The
only conclusion we can draw is that the district court was not satisfied this
was a case of undue hardship, and we will presume the district court did not
find any undue hardship. That determination is one within the sound discretion
of the trial court, and we will not overturn the finding on the issue in the
absence of evidence of clear abuse of the court's discretion. The burden of
providing that proof is assigned to the Board in this case, and the self-serving
conclusion it offers as evidence, since it incorporates no facts whatsoever,
does not meet that goal. In this situation, the district court has not acted in
a manner which exceeds the bounds of reason and certainly could reasonably
conclude as it did. Dynan, 792 P.2d 631, 640. The order for payment in full will
not be amended.
[32.] In summary, we hold the district court
had jurisdiction to confirm the arbitration award in this instance and did not
err in doing so. Westates did not have to satisfy the constitutional
requirements, and the requirements of the Wyoming Governmental Claims Act were
satisfied. The decision of the district court, including the provision for
payment in full, is affirmed.
CARDINE and URBIGKIT, JJ., file dissenting
opinions.
CARDINE, Justice,
dissenting.
[33.] I dissent from the analysis used by the
majority in reaching the conclusion that the Weston County Hospital Joint Powers
Board is not a "political subdivision" as contemplated by Art. 16 7 of the
Wyoming
Constitution. I object for several reasons. First, the majority misinterprets
Witzenburger. Second, reliance on Witzenburger alone is improper due to
important factual differences in this case. Third, the test adopted by the
majority will defeat the clear purpose of this section of the Wyoming
Constitution.
[34.] In its cursory treatment of the
applicable law concerning the constitutional definition for "political
subdivision," the majority states:
The criteria for
identifying a "political subdivision" are found in Witzenburger v. State ex rel.
Wyoming Community Development Authority, 575 P.2d 1100, reh'rg denied, 577 P.2d
1386 (Wyo. 1978). There, we concluded that a "`political subdivision' must be an
entity of the same kind or class as a county, city, township, town or school
district," Witzenburger, 575 P.2d at 1112, and that it would be characterized by
certain distinctive badges including a prescribed geographic area, a requirement
for having officers duly elected by the inhabitants of that area at a public
election, and a legal power to levy and collect taxes. Witzenburger. This is
still the applicable test. While the list we have recited is not all-inclusive,
any "body politic" not possessing at
least these three basic attributes cannot be a "political subdivision." See
Witzenburger.
Maj.
op. at 846 (emphasis added). Witzenburger did not establish a black letter rule
as the majority concludes. Instead, what we said in Witzenburger
was:
We do
not hold that the legislature cannot create a political subdivision but if it
does, it must have those attributes of a political subdivision, within the
contemplation of the Wyoming Constitution, such as we have
outlined.
Witzenburger,
575 P.2d at 1114. The "attributes" outlined in Witzenburger are not as clear and
constrained as the majority suggests. We said:
Each
[political subdivision] has a geographic area smaller than the state, each is
organized with officers elected by its inhabitants to carry on a governmental
function, having a local purpose and provision is made for the levy and
assessment of taxes to finance those purposes.
Witzenburger,
575 P.2d at 1113. We gathered this list of attributes after scrutinizing our
constitutional history and surveying precedent from other jurisdictions.
Witzenburger, 575 P.2d at 1111-12. The test announced by the majority does not
accurately portray and follow the general approach utilized by the Witzenburger
court.
[35.] In addition, Witzenburger differs
factually from this case. The sections at issue in Witzenburger were 1 and 2
of Article 16, not 7. Witzenburger involved the Wyoming Community Development
Authority (WCDA) which was not formed under the Joint Powers Act. Unlike the
WDCA, the Weston County Hospital Joint Powers Board does possess some of the
characteristics outlined by Justice Raper in Witzenburger. The board encompasses
a geographic area smaller than the state (Weston County), and it is organized to carry on a
governmental function and a local purpose (providing accessible modern health
care facilities). Although I agree that Witzenburger does offer guidance on the
issue, by itself, it is not determinative.
[36.] In this particular case, the majority's
analysis may not eviscerate the purpose of Art. 16 7 of the Wyoming
Constitution; but, in the future, I fear it will. The purpose, providing
opportunity to inspect all claims against the State so as to prevent wasting
public funds in useless litigation, is settled. The test adopted today will
allow claims to be brought without sufficient warning against certain
quasi-public entities who are not termed a "political subdivision" but who are
essentially publicly funded.
[37.] Because the majority relies solely upon a
test which it incorrectly elicits from Witzenburger and hastily resolves an
issue of constitutional interpretation, I must dissent from the majority's
analysis of "political subdivision" and the conclusion based upon that
analysis.
URBIGKIT, Justice,
dissenting.
[38.] The centerpiece for this decision
envisions that when two admitted governmental subdivisions join together to
operate an area hospital employing public resources for the citizens of the
area, the resulting entity will no longer constitute a political subdivision.
This is significant because the constitution of the state and the statutes
enacted by the legislature provide protection to citizens who become responsible
for the incurrence of obligations by governmental entities created for their
benefit.
[39.] Leaving aside the advantages for the
contractor who built the public facilities and the loss of control for the
citizens through operation of the joint powers entity, I cannot find, in this
circumstance, any justification for differentiating a political subdivision
(each of the partners) from a governmental entity (the entity used for their
combined public service). A governmental subdivision implies a defined
territorial entity. This is clearly the result in the creation of a joint powers
board when the two admitted political subdivisions join to perform a common
interest public service. The entity will likely accrue financial
responsibilities obligatory upon all of the citizens within the totality of
their geographical area of responsibility. Residents, to get the service, will
be required to provide the necessary funding to pay operational and
constructional obligations.
[40.] I fail to perceive why hospital
operations conducted under the purview of a joint powers board should not be
accorded the same contracting protection for the citizens who are ultimately
responsible as will be the case if the activity is separately operated by only
one of them. There is no question that the county of Weston, exclusive of the towns of Upton and Newcastle, Wyoming, when combined with their territory,
defines a specific taxpayer and political entity geographic territory and,
equivalently, a statutorily-defined political subdivision to conduct a
governmental function. The resulting hospital service is impressed with the
public interest.
[41.] We should not misunderstand what this
decision does. It accords to the citizens and taxpayers of local communities
reduced protection from the conduct of any governmental activity through the
usage of a joint powers board. I fail to see any providence or persuasion that
the legislature intended to reduce protection for the citizenry by authorization
of the creation of joint power districts. Witzenburger v. State ex rel. Wyoming
Community Development Authority, 575 P.2d 1100 (Wyo. 1978) cannot provide a justification for
this diminution of citizenry protection from their governmental entity
incurrence of obligations. Such legislative history as might be available would
reflect that the active, anguished and continued legislative opposition to the
entity envisioned in the litigation discussed in Witzenburger found its views
authenticated by the reversal decision of the Wyoming Supreme
Court.
[42.] Constitutional rejection by this court of
the open ended opportunity to incur liabilities ultimately chargeable to
taxpayers considered in Witzenburger forcefully denies use of that precedent to
approve this decision. I would find Witzenburger philosophically determinative
that combining governmental entities into a joint powers board should not reduce
protection for the citizens. Overtly, a joint powers board has a prescribed
geographical area constituent of the totality of its contributors. The statute
requires officers whose election is accommodated by action of the constituent
partners. We should not kid ourselves that joint power boards have no authority
to levy and collect taxes, albeit perhaps indirectly, since the responsibilities
assumed by the participating governmental parties will ratchet down upon the
citizens of their respective areas if the entity fails in
operation.
[43.] The anguish and concern reflected by the
three-to-two majority in Witzenburger and, in particular, the comments of Chief
Justice Guthrie, do not lead us further in this review than to recognize that
the judgment award countenanced by this decision constitutes a debt imposed upon
each citizen of the constituent joint powers partners in their operation of an
indispensable hospital. The debt appropriately considered by Chief Justice
Guthrie in Witzenburger is no less a debt than is now created for the citizen
users of the hospital by this decision.
[44.] The question with which we are presented
is not whether the state legislature can create obligations that are not those
of the state, Witzenburger, 575 P.2d at 1115, but whether the citizens of this
state in 1889, by adoption of the Wyoming Constitution, provided a debt
incurrence escape for modernized forms of entities used to provide general
governmental services. Without regard for the new form selected for the
operational entity, the taxpayer will, in one way or another, be assessed the
responsibility to pay. Certainly, the very learned persons who joined together
to write the Wyoming Constitution, or even the amendment permitted by a vote of
the citizenry in 1970, contemplated no process where public funds and their use
or misuse might be excepted from the requirement to "be audited, allowed or paid
until a full itemized statement in writing, certified to under penalty of
perjury, shall be filed with the officer or officers whose duty it may be to
audit the same." Wyo. Const. art. 16, 7. If plain meaning
means anything, Allied-Signal, Inc. v. Wyoming State Bd. of Equalization, 813
P.2d 214 (Wyo. 1991), those drafters intended certain unescapable
responsibilities for the expenditures of public funds. Surely no one would
dispute that joint powers boards encompass anything but a governmental operation
in the utilization of public funds.
[45.] The result in this majority's decision is
not particularly earth shaking in dollar amount. The pathway narrowing the
constitutional protection afforded to our citizens is, however, of concern. We
only invite ingenious ways to escape constitutional responsibility for the
protection and preservation of our joint public assets.
[46.] In disagreement that this entity does not
fall within the constitutional limitations and criteria for public protection,
as does other governmental bodies, I respectfully dissent. The hospital
management district, which is the subject matter of this litigation, should be
accorded no different statutory or constitutional perspective regarding
protection to the public interest than was afforded the State Highway Commission
in Utah Const. Co. v. State Highway Commission, 45 Wyo. 403, 19 P.2d 951 (1933),
or the University of Wyoming in Board of Trustees of University of Wyoming v.
Bell, 662 P.2d 410 (Wyo. 1983) and Awe v. University of Wyoming, 534 P.2d 97
(Wyo. 1975). Frankly, it will take something more than a casual mathematician or
perhaps a computer-controlled political scientist to assess among the two score
or more separately defined political entities which districts constitute and are
controlled by the constitution as political subdivisions and which are
constitutionally excepted governmental entities.
[47.] I also do not agree with this majority's
treatment of the clearly defined installment right of payment of the
governmental entity. Somehow we make this a non-debt until it comes time to
require taxpayer contribution. It was accurately recognized by appellant in its
brief that "[t]he purpose of the constitutional provision is to protect
governmental entities from improper or unsupported charges. Houtz v. Board of
Commissioners, 11 Wyo. 152, 70 P. 840
(1902)."
[48.] It is interesting to recognize, as we
pursue this issue of governmental responsibility and citizenry protection, that
the contractor states in his brief:
However,
the confirmed award will not be financed by the Board, but rather by three
distinct political entities with general taxing authority. Paying a share of an
award of $100,000.00 is not likely to impose an "undue" hardship on any one of
them. There is no evidence whatsoever that the payment of the award would
require those entities to impose a "one mill" levy for even one year, much less
ten.[1]
[49.] Without any question, a governmental
entity as defined and protected by the Wyoming Governmental Claims Act, Wyo.
Stat. 1-39-101 through 1-39-120 (1988 & Supp. 1992), includes "joint
powers boards." Wyo. Stat. 1-39-103(a)(ii). It seems incomprehensible, since
the Governmental Claims Act is obviously defined to include this entity, that we
now reject usage of the installment payment provision of Wyo. Stat.
1-39-118(c)(iv).
[50.] Consequently, I
dissent.
FOOTNOTES
1 Once we leave the
broad classifications of the state, the University of Wyoming, the State Highway
Commission, the Game and Fish Commission, etc. and descend into the definable
but not so certain geographical area excluding legislative districting of the
county, the municipality, and the school or college district, we can then
proceed into the weed and pest control districts and the sewer and water
districts and down into the separate or joint governmental entities which
provide hospital, recreational, water, and a considerable variety of additional
community-operated public services. I think we simply fall into a hole and pull
the top in after us when we attempt to define a governmental entity under joint
power authorization to be something different than a governmental subdivision in
order to foreclose regulations by payment and indebtedness limitations
established in variant ways for the basic law of the state in the Wyoming
Constitution.
Citationizer Summary of Documents Citing This Document
Cite | Name | Level | |
---|---|---|---|
Wyoming Supreme Court Cases | |||
Cite | Name | Level | |
1994 WY 100, 882 P.2d 880, | Matter of Cordova | Cited | |
1996 WY 166, 929 P.2d 525, | Peterson v. Sweetwater County School Dist. No. One | Cited | |
1998 WY 8, 952 P.2d 1108, | Routh v. State, ex rel. Wyoming Workers' Compensation Div | Cited | |
1998 WY 20, 954 P.2d 962, | Bailey v. Bailey | Cited | |
1997 WY 74, 938 P.2d 863, | Hermreck v. United Parcel Service, Inc. | Cited |
Cite | Name | Level | |
---|---|---|---|
Wyoming Supreme Court Cases | |||
Cite | Name | Level | |
1902 WY 27, 70 P. 840, 11 Wyo. 152, | Houtz v. Board of Com'rs of Uinta County | Cited | |
1933 WY 14, 19 P.2d 951, 45 Wyo. 403, | Utah Const. Co. v. State Highway Commission | Cited | |
1962 WY 54, 376 P.2d 640, | Oil, Chemical & Atomic Workers Union, Local 2-230 v. Great Lakes Carbon Corp. | Cited | |
1975 WY 15, 534 P.2d 97, | Awe v. University of Wyoming | Cited | |
1977 WY 16, 560 P.2d 1172, | Matter of Town of Greybull | Cited | |
1977 WY 30, 562 P.2d 1017, | American Nat. Bank of Denver v. Cheyenne Housing Authority | Cited | |
1977 WY 105, 572 P.2d 1106, | Frank v. City of Cody | Cited | |
1978 WY 11, 575 P.2d 1100, | Witzenburger v. State ex rel. Wyoming Community DevelopmentAuthority | Discussed at Length | |
1978 WY 34, 577 P.2d 1386, | Witzenburger v. State | Discussed | |
1978 WY 88, 586 P.2d 550, | Merritt v. Merritt | Cited | |
1979 WY 95, 598 P.2d 796, | Worthington v. State | Cited | |
1981 WY 91, 632 P.2d 925, | ABC Builders, Inc. v. Phillips | Cited | |
1982 WY 135, 655 P.2d 265, | Brasel & Sims Const. Co., Inc. v. State Highway Com'n of Wyoming | Cited | |
1983 WY 37, 661 P.2d 1040, | T & M Properties v. ZVFK Architects and Planners | Cited | |
1983 WY 41, 662 P.2d 410, | Board of Trustees of University of Wyoming v. Bell | Cited | |
1983 WY 75, 666 P.2d 957, | Dee v. Laramie County | Discussed | |
1986 WY 24, 713 P.2d 766, | Reliance Ins. Co. v. Chevron U.S.A. Inc. | Cited | |
1989 WY 205, 783 P.2d 144, | BOB BURG AND FRED W. BOEKEL, D/B/A LAKOTA PARTNERSHIP v. RUBY DRILLING CO., INC., JESSE DALE RUBY AND MAX L. RUBY ; RUBY DRILLING CO., INC., JESSE DALE RUBY AND MAX L. RUBY v. BOB BURG AND FRED W. BOEKEL, D/B/A LAKOTA PARTNERSHIP | Cited | |
1990 WY 48, 792 P.2d 631, | Dynan v. Rocky Mountain Federal Sav. and Loan | Cited | |
1989 WY 142, 776 P.2d 742, | IN THE MATTER OF THE ESTATE OF JAMES A. McCUE, deceased. ROBERT A. McCUE v. GEORGE W. McCUE, JAMES E. McCUE, THELMA M. DEXTER, AND MARION L. ALLEN, appellees (objectors), STOCKMENS BANK & TRUST COMPANY of Gillette, Wyoming, Executor of the Estate of JAMES A. McCUE, deceased | Cited | |
1992 WY 107, 837 P.2d 1081, | Jackson State Bank v. Homar | Cited |